Dear sir
What if one of the key stakeholders apologize from attending the kickoff meeting ,
The options
A. Insisting to continue the meeting
B. Cancel the meeting
C. Review the Communication plan
D. Review the stakeholder plan
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®