Does the Define Scope process create Change Requests 1 year 5 months ago #12684

  • Anil Gidwani
  • Anil Gidwani's Avatar Topic Author
  • Offline
  • Junior Boarder
  • Junior Boarder
  • Posts: 25
  • Thank you received: 0
Since the Scope baseline does not exist at the time Define Scope is executed, there is no question of a Change Request required for, for example, changing the requirements documentation due to findings during the scope definition.

Byt PMBOK 5 says (page 132) in Project Documents Updates: If approved change requests result from the Create WBS process, then the requirements documentation may need to be updated to include approved changes.

Very ambiguous, I think. Shouldn't the Create WBS process have Change Requests as an output according to the above statement?
Moderators: Yolanda MabutasScott GillardMary Kathrine PaduaSteven Mudrinich, PMPCynthia Lim Louis, PMPTracy Shagnea, PMPPatrick Floris PhD PMPJoe PangJason YorekLuke HoSimone ChristieAmy MartinezDaniel DewartEmily Rivera

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login
21-Jun-2019: Free PMP Exam Coaching Webinar with Dan Ryan Register Now...