Steven,
Thanks, I understand and have the exam outline PDF. But if I need to study more on "Domain III Task 5" which talks "Risk Management Plan" and you go to page 61 of the PMBOK, look at the Knowledge Area of "11. Project Risk Management" there is nothing listed in the "Executing Process Group".
The "Executing Process Group" has only (4.3 Direct and Manage Project Work, 8.2 Perform Quality Assurance, 9.2 Acquire Project Team 9.3 Develop Project Team 9.4 Manage
Project Team, 10.2 Manage Communications, 12.2 Conduct Procurements 13.3 Manage Stakeholder Engagement) but no info on Risk.