TOPIC: Change requests - a project document?

Change requests - a project document? 1 year 8 months ago #12226

  • Anil Gidwani
  • Anil Gidwani's Avatar Topic Author
  • Offline
  • Junior Boarder
  • Junior Boarder
  • Posts: 25
  • Thank you received: 0
The Plan Risk Response process has the following output:

Project Documents Updates

which lists as one of its components "Change Requests"! (PMBOK v.5, page 348)

My question:

(1) Are Change Requests Project Documents?
(2) Why not simply make them a separate output of this process, as is done for other processes? Why include change requests in project documents?

Is this an evolving area of the PMBOK?

Change requests - a project document? 1 year 7 months ago #12272

  • Steven Mudrinich, PMP
  • Steven Mudrinich, PMP's Avatar
  • Offline
  • Moderator
  • Moderator
  • Posts: 125
  • Karma: 4
  • Thank you received: 20
Anil,

Change requests are project documents, typically consolidated into a change log and electronically stored in most modern change control systems. I can't speak to why the PMBOK Guide doesn't separate it out; it doesn't matter for the exam, simply know that the CCS is used to monitor and control the changes to the project baselines.

- Steven
Moderators: Yolanda MabutasScott GillardMary Kathrine PaduaSteven Mudrinich, PMPCynthia Lim Louis, PMPTracy Shagnea, PMPPatrick Floris PhD PMPJoe PangJason YorekLuke HoSimone ChristieAmy MartinezDaniel DewartEmily Rivera

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login
21-Jun-2019: Free PMP Exam Coaching Webinar with Dan Ryan Register Now...