Manage Stakeholder Engagement - No stakeholder register? 6 years 6 months ago #12210

  • Anil Gidwani
  • Anil Gidwani's Avatar Topic Author
  • Offline
  • Junior Boarder
  • Junior Boarder
  • Posts: 25
  • Thank you received: 0
It is quite unexpected to see that the stakeholder register is NOT an input to the Manage Stakeholder Engagement process. Any reason why this is so? The stakeholder register contains valuable information to facilitate the management of stakeholder relationships.

Manage Stakeholder Engagement - No stakeholder register? 6 years 6 months ago #12234

  • STEVEN HOBMANN
  • STEVEN HOBMANN's Avatar
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 1
  • Thank you received: 0
I think the distinction here is the difference between planning and doing. Managing stakeholders is done during execution with a focus on managing expectations and dealing with concerns and issues. The key stakeholders you will be "managing" has already been captured in the Stakeholder Management Plan.

Manage Stakeholder Engagement - No stakeholder register? 6 years 6 months ago #12235

  • Ahmed Amin
  • Ahmed Amin's Avatar
  • Offline
  • Gold Boarder
  • Gold Boarder
  • Posts: 300
  • Karma: 10
  • Thank you received: 73
the stakeholder register is part of the stakeholder management plan which is an input to the manage stakeholder engagement process.

please check the section "13.2.3.1 Stakeholder Management Plan" it states the below:

The stakeholder management plan is a component of the project management plan (Section 4.2.3.1) and identifies the management strategies required to effectively engage stakeholders. The stakeholder management plan can be formal or informal, highly detailed or broadly framed, based on the needs of the project.

In addition to the data gathered in the stakeholder register, the stakeholder management plan often provides:
Ahmed Amin Abdullah, PMP
Community Moderator

Manage Stakeholder Engagement - No stakeholder register? 6 years 2 months ago #13058

  • Humberto
  • Humberto's Avatar
  • Visitor
  • Visitor
If it is true that stakeholder register is a part ok Stakeholder Management Plan, then it is contradictory and redundant that "Plan Stakeholder Management" receives the Project Management Plan (including Stakeholder Management Plan) and Stakeholder register.....It seems that Stakeholder register is received twice here....
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaDaniel SoerensenElena ZelenevskaiaChristian ElmerChristine Whitney, PMP

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login