fbpx
Do you need customer support or technical assistance? Click here to submit a support ticket...

TOPIC: PMP - Decision Tree Question

PMP - Decision Tree Question 6 years 7 months ago #11678

  • Monique Maxmillion
  • Monique Maxmillion's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 4
  • Thank you received: 0
You are asked to choose between two projects A or B based on the highest gain (or
the lowest loss). A will cost U.S. $650,000 and B will cost U.S. $467,000. There is a
56% chance that project A will be successful, which will result in a gain of U.S.
$1,800,000. If project A fails there will be a loss of U.S. $900,000. There is a 67%
project B will be successful, and that will result in a U.S. $950,000 gain. If Project B
fails there will be a loss of U.S. $670,000. Based on this information, what is the
value of the best alternative?
A. U.S. $-38,000
B. U.S. $38,000
C. U.S. $-51,600
D. U.S. $51,600

PMP - Decision Tree Question 6 years 3 months ago #12908

  • Aghalar
  • Aghalar's Avatar
  • Visitor
  • Visitor
Answer A

PMP - Decision Tree Question 6 years 1 month ago #13592

  • yasmin
  • yasmin's Avatar
  • Visitor
  • Visitor

Monique Maxmillion wrote: You are asked to choose between two projects A or B based on the highest gain (or
the lowest loss). A will cost U.S. $650,000 and B will cost U.S. $467,000. There is a
56% chance that project A will be successful, which will result in a gain of U.S.
$1,800,000. If project A fails there will be a loss of U.S. $900,000. There is a 67%
project B will be successful, and that will result in a U.S. $950,000 gain. If Project B
fails there will be a loss of U.S. $670,000. Based on this information, what is the
value of the best alternative?
A. U.S. $-38,000
B. U.S. $38,000
C. U.S. $-51,600
D. U.S. $51,600

PMP - Decision Tree Question 5 years 9 months ago #14619

  • Anonymous
  • Anonymous's Avatar
  • Visitor
  • Visitor
A

PMP - Decision Tree Question 5 years 3 months ago #16292

  • Mengis
  • Mengis's Avatar
  • Visitor
  • Visitor
The answer is as stated above.
Here is break down :
Apply the EVM equation :
Project A. -$650,000 +(56% *×1,800,000 ) + (-44% of the $900,000) = -$38,000
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaDaniel SoerensenAlexander AnikinElena ZelenevskaiaChristian ElmerChristine Whitney, PMP

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login