Do you need customer support or technical assistance? Click here to submit a support ticket...

TOPIC: PMP - Decision Tree Question

PMP - Decision Tree Question 3 years 3 weeks ago #11678

  • Monique Maxmillion
  • Monique Maxmillion's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 4
  • Thank you received: 0
You are asked to choose between two projects A or B based on the highest gain (or
the lowest loss). A will cost U.S. $650,000 and B will cost U.S. $467,000. There is a
56% chance that project A will be successful, which will result in a gain of U.S.
$1,800,000. If project A fails there will be a loss of U.S. $900,000. There is a 67%
project B will be successful, and that will result in a U.S. $950,000 gain. If Project B
fails there will be a loss of U.S. $670,000. Based on this information, what is the
value of the best alternative?
A. U.S. $-38,000
B. U.S. $38,000
C. U.S. $-51,600
D. U.S. $51,600

PMP - Decision Tree Question 2 years 7 months ago #12908

  • Aghalar
  • Aghalar's Avatar
  • Visitor
  • Visitor
Answer A

PMP - Decision Tree Question 2 years 6 months ago #13592

  • yasmin
  • yasmin's Avatar
  • Visitor
  • Visitor

Monique Maxmillion wrote: You are asked to choose between two projects A or B based on the highest gain (or
the lowest loss). A will cost U.S. $650,000 and B will cost U.S. $467,000. There is a
56% chance that project A will be successful, which will result in a gain of U.S.
$1,800,000. If project A fails there will be a loss of U.S. $900,000. There is a 67%
project B will be successful, and that will result in a U.S. $950,000 gain. If Project B
fails there will be a loss of U.S. $670,000. Based on this information, what is the
value of the best alternative?
A. U.S. $-38,000
B. U.S. $38,000
C. U.S. $-51,600
D. U.S. $51,600

PMP - Decision Tree Question 2 years 2 months ago #14619

  • Anonymous
  • Anonymous's Avatar
  • Visitor
  • Visitor
A

PMP - Decision Tree Question 1 year 8 months ago #16292

  • Mengis
  • Mengis's Avatar
  • Visitor
  • Visitor
The answer is as stated above.
Here is break down :
Apply the EVM equation :
Project A. -$650,000 +(56% *×1,800,000 ) + (-44% of the $900,000) = -$38,000
Moderators: Yolanda MabutasMary Kathrine PaduaCynthia Lim Louis, PMPTracy Shagnea, PMPGabriella Dellino, PMPPatrick Floris PhD PMPJoe PangJohn Paul BugarinAmy MartinezEmily Rivera, PMPLisa Sweeney PMPHarry ElstonMani SelvanDenver MartinEric Wanyutu Kahiga, PMPSarah FucciThiago França, PMP®Felix Kamanga, PMPChan RampersaudElena MekhanoshinaKyle Kilbride, PMP

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login