Do you need customer support or technical assistance? Click here to submit a support ticket...

TOPIC: A question on ETC

A question on ETC 2 years 1 month ago #11409

  • Puneet Maheshwari
  • Puneet Maheshwari's Avatar Topic Author
  • Offline
  • Junior Boarder
  • Junior Boarder
  • Posts: 26
  • Thank you received: 1
Hi

Can any one explain, why PV= 250,000X2 = 500,000 and SPI is not considered in below calculation.

I tried to use formula EAC= BAC/(SPI* CPI)

Please advise....


============
Question: You are working on a 12 month assignment to build a website with 4,000 pages for $1,000,000. You are supposed to spend $250,000 every 3 months. After 6 months, you determine that only $400,000 of work is completed and cost incurred is $800,000. What is the ETC?

Choice 1. $2,000,000

Choice 2. $1,500,000

Choice 3. $1,000,000

Choice 4. $1,200,000

Correct Choice: 4

Justification



The default value of EAC (assuming current variances are typical) is calculated as below:

CPI = EV/AC
CPI = $400,000 / $800,000
CPI = 0.5

EAC = BAC/CPI
EAC = $1,000,000/0.5
EAC = $2,000,000

So, ETC = EAC – AC = $2,000,000 – $800,000 = $1,200,000

Reference: PMstudy.com comments

============

A question on ETC 2 years 1 month ago #11423

  • Tracy Shagnea, PMP
  • Tracy Shagnea, PMP's Avatar
  • Offline
  • Moderator
  • Moderator
  • Posts: 110
  • Karma: 6
  • Thank you received: 42
Hi Puneet,

With regard to your questions:


Can any one explain, why PV= 250,000X2 = 500,000


The planned spending is $250,000 every 3 months. Since the calculation is taking place at the end of 6 months, then the PV is for 2 time periods, which yields 2 x $250,000 = $500,000

SPI is not considered in below calculation


Because the question does not indicate that a deadline exists for completion, we would not use SPI, hence the EAC= BAC/(SPI* CPI) formula is not appropriate for this particular scenario. It will yield a much higher cost. The question is a wee bit tricky, since they do give you enough information to calculate the SPI, even though it is not needed for the given scenario.

I hope this helps!

Regards,

Tracy
Forum Moderator
PMP, CSM, M.S. Management
Moderators: Yolanda MabutasScott GillardMary Kathrine PaduaSteven Mudrinich, PMPCynthia Lim Louis, PMPTracy Shagnea, PMPPatrick Floris PhD PMPJoe PangJohn Paul BugarinJason YorekLuke HoSimone ChristieAmy MartinezDaniel DewartEmily RiveraMani Selvan

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login