fbpx
Do you need customer support or technical assistance? Click here to submit a support ticket...

TOPIC: Why critical Path is shortest project duration?

Why critical Path is shortest project duration? 6 years 9 months ago #11333

  • Puneet Maheshwari
  • Puneet Maheshwari's Avatar Topic Author
  • Offline
  • Junior Boarder
  • Junior Boarder
  • Posts: 26
  • Thank you received: 1
Critical path is longest path on a network diagram.

However it is also called shortest project duration... How?

Thanks
Puneet

Why critical Path is shortest project duration? 6 years 8 months ago #11616

  • Gail Freedman
  • Gail Freedman's Avatar
  • Offline
  • Junior Boarder
  • Junior Boarder
  • Posts: 35
  • Karma: 2
  • Thank you received: 3
Hi Puneet,

Yes, the critical path is the longest overall duration for the sequenced activities. It is not the shortest project duration and it is the shortest time possible to complete the project. Hope that helps.

Thanks,
Gail
Gail Freedman, MBA, PMP, CSM

Why critical Path is shortest project duration? 4 years 2 months ago #20142

  • Anonymous
  • Anonymous's Avatar
  • Visitor
  • Visitor
Sorry,
Please elaborate the difference between time and duration? I didn't get your reply....!

Why critical Path is shortest project duration? 4 years 1 month ago #20146

  • Harry Elston
  • Harry Elston's Avatar
  • Offline
  • Moderator
  • Moderator
  • Posts: 457
  • Karma: 27
  • Thank you received: 144
Anon: Let me try:

Tasks A, B, C and D all take 5 days.

A must be before B and C can start. D is the final task B and C can be run in parallel after A. The Network Diagram is:

A --> B/C --->D

The critical path is 15 days, not 20, because B and C can be done simultaneously (Afer A)

Hope that helps.

Harry
+++++
Harry J. Elston, Ph.D., CIH, PMP

Why critical Path is shortest project duration? 4 years 1 month ago #20160

  • Anantha Narayanan Santhanagopalan
  • Anantha Narayanan Santhanagopalan's Avatar
  • Offline
  • Junior Boarder
  • Junior Boarder
  • Posts: 39
  • Karma: 3
  • Thank you received: 7
Hi Anonymous,

Take this example - Dining with friends.

You all go for dinner (say 3 people). Everyone orders food and start eating...
Person 1 - Takes 45 mins for eating
Person 2 - Takes 20 mins for eating
Person 3 - Takes 55 mins for eating.

Everyone can leave only after person 3 completes his/her food.

So the longest path would be reaching restaurant --> Ordering food --> Person 3 finishing the dinner --> paying bills
This is also the shortest time they can complete the dining.

Now lets explain float as well
Person 3 cannot have any slack. Meaning - he cannot attend any phone calls/use restroom, if he/she does take a break it will still delay the dining.
Whereas person 2 and person 1 can take a break/do other things while they are eating.
So activities in critical path ideally cannot have float.

Hope this helps.

Regards,
Anantha
The following user(s) said Thank You: Gabriella Dellino, PMP, Ujwala Karanam, Elizabeth Harrin, Jack Lee

Why critical Path is shortest project duration? 3 years 6 months ago #24020

  • To amantha
  • To amantha's Avatar
  • Visitor
  • Visitor
you are a darling for that response....THANK YOU

[email protected] 3 years 6 months ago #24021

  • Anonymous
  • Anonymous's Avatar
  • Visitor
  • Visitor
THANK YOU ANANTHA

Why critical Path is shortest project duration? 2 years 1 month ago #29177

  • Anonymous
  • Anonymous's Avatar
  • Visitor
  • Visitor
lovely example Anantha!!!

Why critical Path is shortest project duration? 2 years 1 month ago #29194

  • Anonymous
  • Anonymous's Avatar
  • Visitor
  • Visitor
Thank you so much.
This made my day
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaDaniel SoerensenAlexander AnikinElena ZelenevskaiaChristian ElmerChristine Whitney, PMP

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login