TOPIC: Where is Release resource and team member performance performed?

Where is Release resource and team member performance performed? 6 years 9 months ago #11322

  • Puneet Maheshwari
  • Puneet Maheshwari's Avatar Topic Author
  • Offline
  • Junior Boarder
  • Junior Boarder
  • Posts: 26
  • Thank you received: 1
Is release resources performed during Executing Process group (a manage team as per Rita process chart) or closing process group?

Is team member performance done in executing ( manage team pmbok page282) or closing (pmbok page 58)?

Where is Release resource and team member performance performed? 6 years 8 months ago #11618

  • Gail Freedman
  • Gail Freedman's Avatar
  • Offline
  • Junior Boarder
  • Junior Boarder
  • Posts: 35
  • Karma: 2
  • Thank you received: 3
Hello Puneet,

Release resources occurs in the closing process group. Team performance assessment is in executing.

- Gail
Gail Freedman, MBA, PMP, CSM

Where is Release resource and team member performance performed? 6 years 3 months ago #12872

  • ELOUNDOU
  • ELOUNDOU's Avatar
  • Visitor
  • Visitor
releasing the project team is no longer part of closing, according the new RDS study conducted by PMI. This was amended in 2011.
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaDaniel SoerensenAlexander AnikinElena ZelenevskaiaChristian ElmerChristine Whitney, PMP

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login