If a team member working on a non critical path activity (float 4 days) gets delayed by 2 days. -- no change in project duration hence no baseline change.... Hence no need of PICC
for the example you stated, of course No, CCB will not be involved in such changes or similar things that are considered daily work of a PM. the CCB will concerned only if the project baselines (schedule, scope, cost) or constraints (quality, resources, risks) might be affected.
I know that change that impact baselines have to go through PICC which means it has to be approved by the change control board (CCB). What about change s that are determined to not impact baselines. ? Should they go to the CCB for approval as part of the PICC process.
e.g. If a team member working on a non critical path activity (float 4 days) gets delayed by 2 days. While this will not impact the schedule baseline it will still require update sto the project schedule or milestone list . Would this change have to go through PICC. If yes, would it go to the change control board ?
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®