TOPIC: Changes that do not impact baselines have to go through PICC or not ?

Changes that do not impact baselines have to go through PICC or not ? 2 years 2 months ago #11285

  • mavs19
  • mavs19's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 8
  • Karma: 1
  • Thank you received: 0
Hi :

I know that change that impact baselines have to go through PICC which means it has to be approved by the change control board (CCB). What about change s that are determined to not impact baselines. ? Should they go to the CCB for approval as part of the PICC process.

e.g. If a team member working on a non critical path activity (float 4 days) gets delayed by 2 days. While this will not impact the schedule baseline it will still require update sto the project schedule or milestone list . Would this change have to go through PICC. If yes, would it go to the change control board ?

Changes that do not impact baselines have to go through PICC or not ? 2 years 2 months ago #11293

  • Ahmed Amin
  • Ahmed Amin's Avatar
  • Offline
  • Gold Boarder
  • Gold Boarder
  • Posts: 300
  • Karma: 8
  • Thank you received: 72
for the example you stated, of course No, CCB will not be involved in such changes or similar things that are considered daily work of a PM. the CCB will concerned only if the project baselines (schedule, scope, cost) or constraints (quality, resources, risks) might be affected.
Ahmed Amin Abdullah, PMP
Community Moderator
The following user(s) said Thank You: Lhito Jose

Changes that do not impact baselines have to go through PICC or not ? 2 years 1 month ago #11317

  • Stan Po, MBA, PMP, PMI-ACP, CSM
  • Stan Po, MBA, PMP, PMI-ACP, CSM's Avatar
  • Offline
  • Administrator
  • Administrator
  • Posts: 287
  • Karma: 3
  • Thank you received: 41
Dear mavs19,

There is another post in our forum that addresses this topic. You may check it here:

www.project-management-prepcast.com/kune...cuments-updates#9358
Regards,
Stan

Changes that do not impact baselines have to go through PICC or not ? 2 years 1 month ago #11325

  • Puneet Maheshwari
  • Puneet Maheshwari's Avatar
  • Offline
  • Junior Boarder
  • Junior Boarder
  • Posts: 26
  • Thank you received: 1
If a team member working on a non critical path activity (float 4 days) gets delayed by 2 days. -- no change in project duration hence no baseline change.... Hence no need of PICC
Moderators: Yolanda MabutasScott GillardMary Kathrine PaduaSteven Mudrinich, PMPCynthia Lim Louis, PMPTracy Shagnea, PMPPatrick Floris PhD PMPJoe PangJohn Paul BugarinJason YorekLuke HoSimone ChristieAmy MartinezDaniel DewartEmily RiveraMani Selvan

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login
Boost Your PMP Exam Prep in Only Eight Hours! Join the Live PMP Coaching Class on September 21/22 for just $179. Click to learn more... OR Click to watch a free session...