TOPIC: A question about Risk

A question about Risk 6 years 9 months ago #11122

  • Sameh Elgendy
  • Sameh Elgendy's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 7
  • Thank you received: 0
Do insufficient resources consider a risk ?

A question about Risk 6 years 9 months ago #11124

  • Mukti Roy
  • Mukti Roy's Avatar
  • Visitor
  • Visitor
Yes.

A question about Risk 6 years 9 months ago #11126

  • Ahmed Amin
  • Ahmed Amin's Avatar
  • Offline
  • Gold Boarder
  • Gold Boarder
  • Posts: 300
  • Karma: 10
  • Thank you received: 73
resources is one of the major sources for Risks in any project whether it is related to resources availability, quality, skills, etc.
but be reminded that a risks are the uncertain events that if occured will affect the project. but if it is a fact, then it is called an issue.
Ahmed Amin Abdullah, PMP
Community Moderator
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaDaniel SoerensenElena ZelenevskaiaChristian ElmerChristine Whitney, PMP

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login