I´ve just done the self-assestment 12 in PrepCast (Procurement Management) and I have a question about question 10:
Question 10: A leading telecom network operator has signed a procurement contract with an international telecom equipment vendor company to extend their network infrastructure nationally by 50%. Network planning, civil works and equipment installation are all included as a part of the procurement contract. From the equipment vendor’s point of view, which of the following needs to be applied efficiently to effectively manage this procurement contract?
A.) Procurement Management
B.) Project Management
C.) Program Management
D.) Portfolio Management
B is the correct answer and, although I understand that it´s from the vendor´s point of view I would have said C because the contract includes not just one Project, but a group of related projects such as civil work, equipment instalation and so on. I guess I am misunderstanding something here. Could you please give me a hand?