Hi daniel,
I would agree with your comment, but I am not sure what is the right channel to communicate erratum.
7 years 6 months ago #8175

Daniel Blossey

Daniel Blossey's Avatar

Correct? Thanks!
7 years 7 months ago #8148

Daniel Blossey

Daniel Blossey's Avatar

Dear Cornelus Fichtner,

in the PM_PrepCast_Student_Workbook_v1.10.pdf there is a mistake below “L05.06 - Control Scope”:

wrong:
  • “First we need to execute a variance analysis by comparing the project management plan, configuration management plan, and change management plan against our scope baseline.”

correct:
  • “First we need to execute a variance analysis by comparing the project management plan (scope baseline, configuration management plan, change management plan) against our work performance data.”

Reason:
  • The scope baseline is part of the project management plan.

OK?