TOPIC: Determining Budget and Procurement

Determining Budget and Procurement 7 years 8 months ago #8063

  • Warren Rutledge
  • Warren Rutledge's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 5
  • Thank you received: 0
I am having a problem understanding how the determine budget process works without and inputs from procurement. In my mind, the budget has to support equipment purchases and such. Where am I missing the boat?

Please help.

Regards.

Determining Budget and Procurement 7 years 8 months ago #8064

  • Ahmed Amin
  • Ahmed Amin's Avatar
  • Offline
  • Gold Boarder
  • Gold Boarder
  • Posts: 300
  • Karma: 10
  • Thank you received: 73
Hi Warren,
one of the main inputs to determine budget process is the "Activity Cost Estimates", if you refer back to section 7.2.3.1 in the PMBOK guide, you will find that activity cost estimates" includes, but is not limited to, direct labor, materials, equipment, services, facilities, information technology, and special categories such as cost of financing (including interest charges), an inflation allowance, exchange rates, or a cost contingency reserve. Indirect costs, if they are included in the project estimate, can be included at the activity level or at higher levels."

hope this helps.
Ahmed Amin Abdullah, PMP
Community Moderator
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaDaniel SoerensenAlexander AnikinElena ZelenevskaiaChristian ElmerChristine Whitney, PMP