Do you need customer support or technical assistance? Click here to submit a support ticket...
  • Page:
  • 1

TOPIC: Question Why not ACTIVITY LIST be used instead of WBS for Estimating Costs?

Why not ACTIVITY LIST be used instead of WBS for Estimating Costs? 1 year 10 months ago #7637

  • Sarmistha Biswas
  • Sarmistha Biswas's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 10
  • Thank you received: 4
Hi,

I would like to know that is there a specific reason that we don't use activity list but WBS to estimate cost?

I know that WBS has related control accounts and gives work package wise information but isn't it better to have further granulated level information using activity list to estimate the cost?

Thanks in advance for your response.
  • Page:
  • 1
Moderators: Yolanda MabutasTimothy EnallsScott GillardMary Kathrine PaduaERIC BARTLETTKevin NasonSteven Mudrinich, PMPMark Wuenscher, PMPJohn WolvertonTracy Shagnea, PMPJada GarrettMark LacattivaPatrick Floris PhD PMPTy Weston, PMPGenevieve Pluviose, PMP

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login