In a multi phased project, If any one of the phases of the project gets terminated/cancelled then
1) Does it mean the entire project is closed?
2) If the entire project is not closed will the close phase process group be different from close project process group?

Close Phase question 1 year 1 week ago #7586

  • Satya Sitharam Nandiraju
  • Satya Sitharam Nandiraju's Avatar
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 18
  • Thank you received: 2
Hi Harish

As per my understanding

1. If any one of the phases closed it doesn't mean entire project is closed.
2. There may be multiple phases in a project, close project means conclusion of all phases as well as entire project. Hence, close phase is concerned only with that particular phase.
Hope it clarifies.

Close Phase question 1 year 1 week ago #7612

  • Yasir Mehmood
  • Yasir Mehmood's Avatar
  • Offline
  • Junior Boarder
  • Junior Boarder
  • Posts: 38
  • Karma: 2
  • Thank you received: 11
I agree, that is in line with my understanding and experience as well.
Yasir Mehmood, MBA, PMP, PMI-ACP, CSM, CSP, CLP (LeSS), CSPO
Community Moderator
  • Page:
  • 1
Moderators: Yolanda MabutasAhmed AminScott GillardMichael DeCiccoMary Kathrine PaduaERIC BARTLETTGail FreedmanKevin NasonSteven Mudrinich, PMPMark Wuenscher, PMPJohn WolvertonTracy Shagnea, PMPJada Garrett

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®