TOPIC: Difference between Crashing and Fast Tracking.

Difference between Crashing and Fast Tracking. 14 years 8 months ago #475

  • Chan Krish
  • Chan Krish's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 9
  • Thank you received: 0
Hi All,

I have been trying to understand the difference between Crashing and Fast tracking. Following are my understanding and questions:

Understanding:
Fast tracking means that you look at activities that are normally done in sequence and assign them instead partially in parallel. If you were fast-tracking, you would start constructing the solution in areas where you felt the design was pretty solid without waiting for the entire design to be completed.

"Crashing" the schedule means to throw additional resources to the critical path without necessarily getting the highest level of efficiency. For instance, let’s say one person was working on a ten-day activity on the critical path. If you were really desperate to shorten this timeframe, you might add a second resource to this activity.

Similarities are:
1) Both the approaches are aimed at reducing the schedule
2) Both the approaches require addition of resources to achieve the goal
3) Even though fast tracking doesn't mention the term Critical Path, it's obvious that the Critical Path tasks need to be done in parallel to reduce the schedule. So, both the approaches involve changes to Critical Path activities schedule.

Given the above, both of them looks similar with no subtle difference. But, the two different terms should have been created for a purpose, that i might be missing here.

Thanks!

Re:Difference between Crashing and Fast Tracking. 14 years 8 months ago #476

  • Cornelius Fichtner
  • Cornelius Fichtner's Avatar
  • Offline
  • Administrator
  • Administrator
  • President, OSP International LLC
  • Posts: 1982
  • Karma: 119
  • Thank you received: 606
Chandrasekaran,

Please watch Episode 6.05.2 Develop Schedule. We take about 10 minutes to explain the attributes of and differences between fast tracking and crashing. I cannot really explain it any better than I did there.

But here are a few notes:
- Crashing and fast tracking is ALWAYS on the critical path.
- Crashing adds cost that may not be in your budget.
- Fast tracking adds risk
- Fast tracking does NOT add resources. But you will start work sooner, so resources that were scheduled to be utilized later may have to start earlier in the project.
- If you crash and don't get efficiency you might just as well not do it. So it has to be efficient and cost effective.
Until Next Time,
Cornelius Fichtner, PMP, CSM
President, OSP International LLC

Re:Difference between Crashing and Fast Tracking. 14 years 8 months ago #477

  • Chan Krish
  • Chan Krish's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 9
  • Thank you received: 0
Thanks Cornelius for the quick reply.

Let me watch the episode again.
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaDaniel SoerensenAlexander AnikinElena ZelenevskaiaChristian ElmerChristine Whitney, PMP

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login