Sample Exam Question from April 18th newsletter 7 months 2 weeks ago #7322

  • Jim Fisher
  • Jim Fisher's Avatar
I read the Exam sample question and after clicking on the link to see the answer it says the correct answer is A, but then goes on to say that "Using a Cost Plus Incentive Fee contract will help you control the contractor."
So ... is the correct answer A or B? I was leaning toward B before I looked the answer and don't really want to have to micromanage any of my sub-contractors.
Jim

Sample Exam Question from April 18th newsletter 7 months 2 weeks ago #7323

  • Mary Kathrine Padua
  • Mary Kathrine Padua's Avatar
  • Offline
  • Administrator
  • Posts: 87
  • Thank you received: 44
  • Karma: 3
Hi Jim,

The correct answer is B (Use a Cost Plus Incentive Fee Contract). I accidentally typed A instead of B. I'm very sorry for the confusion.
Moderators: Yolanda Mabutas, Ahmed Amin, Scott Gillard, Michael DeCicco, Rahul Kakkar, Fernando Jr Sinlao Lim, Mary Kathrine Padua, Chris Preziotti, Lazard Toe, ITBMC, MPM, CIPM, PMP, ITIL, Christian Winter, Kevin Nason, Michael Sumaquial, PMP, Mark Wuenscher, PMP

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®