Sample Exam Question from April 18th newsletter 1 year 2 months ago #7322

  • Jim Fisher
  • Jim Fisher's Avatar Topic Author
  • Visitor
  • Visitor
I read the Exam sample question and after clicking on the link to see the answer it says the correct answer is A, but then goes on to say that "Using a Cost Plus Incentive Fee contract will help you control the contractor."
So ... is the correct answer A or B? I was leaning toward B before I looked the answer and don't really want to have to micromanage any of my sub-contractors.
Jim

Sample Exam Question from April 18th newsletter 1 year 2 months ago #7323

  • Mary Kathrine Padua
  • Mary Kathrine Padua's Avatar
  • Offline
  • Administrator
  • Administrator
  • Posts: 116
  • Karma: 3
  • Thank you received: 52
Hi Jim,

The correct answer is B (Use a Cost Plus Incentive Fee Contract). I accidentally typed A instead of B. I'm very sorry for the confusion.
  • Page:
  • 1
Moderators: Yolanda MabutasAhmed AminScott GillardMichael DeCiccoMary Kathrine PaduaERIC BARTLETTGail FreedmanKevin NasonSteven Mudrinich, PMPMark Wuenscher, PMPJohn WolvertonTracy Shagnea, PMPJada Garrett

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®