Welcome, Guest
Do you need customer support or technical assistance? Click here to submit a support ticket...

TOPIC: Stakeholder question

Stakeholder question 6 months 1 week ago #7279

  • Linglish
  • Linglish's Avatar
Why is the communication management plan not an input to plan stakeholder management? Wouldn't you often appoint specific people to communicate with specific stakeholders ? It happens at my work all the time...issues have to go through the proper channels, and often communication with stakeholders is reserved for whomever is closer to them in the channel.

Test is on Monday!

Stakeholder question 6 months 1 week ago #7281

  • Ahmed Amin
  • Ahmed Amin's Avatar
  • Offline
  • Moderator
  • Posts: 191
  • Thank you received: 41
  • Karma: 7
Hi Linglish, Good luck with your exam.

regarding your question, the first input to stakeholder management is the well known commonly used input "Project management plan" which by definition includes all other subsidiary plans including the communication management plan. hope this clears your confusion.

reference: check section from the latest PMBOK guide version. It describes why the Project management plan is an input to the stakeholder management, one of them is "Need and techniques for communication among stakeholders".
Ahmed Amin Abdullah, PMP
Community Moderator
Moderators: Yolanda Mabutas, Ahmed Amin, Michael DeCicco, Rahul Kakkar, Fernando Jr Sinlao Lim, Jeremy Raelin, Mary Kathrine Padua, Yasir Mehmood, Chris Preziotti, Lazard Toe, ITBMC, MPM, CIPM, PMP, ITIL, Christian Winter, Kevin Nason, Michael Sumaquial, PMP, Mark Wuenscher, PMP