PMP Exam's questions 9 months 1 week ago #6830

  • Habib Gailan
  • Habib Gailan's Avatar
1-Project got its final prodcut verified and accepted and PM will be leaving for 2 weeks and team want to celebrate sucess ...what he has to do before leaving?
- take team to lauch for celebration OR
-Start project closing process??
2- As an offer to reduce the cost of many defacts ...in which you have to invest

Testing or inspection??

3-acceptance of IT product was accepted without code verification...this is will most likely be aproblem of which phase/stage?/
warranty or inspection stage??


PMP Exam's questions 8 months 2 weeks ago #6961

  • Chris Preziotti
  • Chris Preziotti's Avatar
  • Offline
  • Moderator
  • Posts: 22
  • Thank you received: 5
  • Karma: 2
Hi Habib,

All three of these questions touch upon some core "PMI"-isms that should definitely be understood:
1) A project isn't done until the Closing processes are complete, i.e. just because the final deliverable has been accepted, doesn't mean your job as a project manager is done!
2) You can't inspect in quality, i.e. address quality concerns before inspection! (the earlier the better)

Knowing these two concepts will help you answer your questions.
Chris Preziotti, PMP
Community Moderator