Welcome, Guest
Do you need customer support or technical assistance? Click here to submit a support ticket...

TOPIC: During which process are risk response plans implemented?

During which process are risk response plans implemented? 11 months 4 days ago #6752

  • David Kornaros
  • David Kornaros's Avatar
  • Offline
  • Fresh Boarder
  • Posts: 11
  • Karma: 0
The PMBOK guide reads (p349) "Control Risks is the process of implementing risk response plans..."
But it also reads (p 81) "Direct and Manage Project work activities include, but are not limited to... manage risks and implement risk response activities".

So which process implements risk responses? Control Risks or Direct and Manage Project work?

During which process are risk response plans implemented? 11 months 4 days ago #6755

  • Michael DeCicco
  • Michael DeCicco's Avatar
  • Offline
  • Moderator
  • Posts: 114
  • Thank you received: 28
  • Karma: 1
David, I understand where the confusion might lie.
First, let's establish a basis. The Risk Management Knowledge Area does not include any Executing Process Group activities. Review Table 3-1, 5th Edition, p. 61.
Second, now here you have the PMBOK telling us we should implement our risk response plan in the Monitor and Control Process. Okay, great, but how do you actually implement all those activities in the Executing Process Group without a Risk Management Knowledge task under that Process Group?
Third, the PMBOK answers that question by directing us to implement those risk response plan activities in the Direct and Manage Project Work task within the Project Integration Management knowledge area.

Does this answer your question?
Yours Respectfully
Michael DeCicco, PMP
Community Moderator

During which process are risk response plans implemented? 11 months 4 days ago #6762

  • Jay Fitzgerald
  • Jay Fitzgerald's Avatar
  • Offline
  • Fresh Boarder
  • Posts: 11
  • Karma: 0
I agree with Michael! Risk Response plans are implemented in Direct & Manage Project Work.

I also had trouble with this. When I took the PM PrepCast, I took Cornelius' advice and I skipped the lessons on the Integration knowledge area and studied all of the other knowledge areas first. Then I came back to Integration. This process helped me to understand how integration incorporates all of the knowledge areas into one cohesive whole. I will assume that PMI has Integration as the first knowledge area because it starts of talking about the first step to a project in establishing a project charter. However, I believe they should change this and have it as the last process right after stakeholders.
Moderators: Yolanda Mabutas, Ahmed Amin, Scott Gillard, Michael DeCicco, Rahul Kakkar, Fernando Jr Sinlao Lim, Mary Kathrine Padua, Chris Preziotti, Lazard Toe, ITBMC, MPM, CIPM, PMP, ITIL, Christian Winter, Kevin Nason, Michael Sumaquial, PMP, Mark Wuenscher, PMP

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®