TOPIC: Closing question

Closing question 11 months 1 week ago #6749

  • Habib
  • Habib's Avatar
habib gailan

Dec 26, 17:20



Hi There,

A confusion has came up with what is the last step in project closure, based on Rita's chart is " lesson learned" but based on your answer to the question you mentioned archiving??

please confirm

thx,

Closing question 11 months 1 week ago #6760

  • Tracey South
  • Tracey South's Avatar
  • Offline
  • Expert Boarder
  • Posts: 131
  • Thank you received: 27
  • Karma: 5
Habib:

Can you provide more information in your question? To whom and what question are you referring to?

Tracey
Community Moderator

Closing question 11 months 1 week ago #6764

  • Cecil D'Souza
  • Cecil D'Souza's Avatar
  • Offline
  • Junior Boarder
  • Posts: 31
  • Thank you received: 6
  • Karma: 0
I think the last step in project closure is releasing the team. Till such time, the project manager may need the team for any other activities related to closure - documentation, archiving etc. That is what I believe.

Closing question 11 months 6 days ago #6772

  • habib
  • habib's Avatar
So to be clear, if there are two choices at closing project FOR LAST ACTIVITY ACTION TO BE DONE :
1- Archiving
2- lesson learned

which one we choose ??

Thanks,

Closing question 11 months 1 day ago #6799

  • Cecil D'Souza
  • Cecil D'Souza's Avatar
  • Offline
  • Junior Boarder
  • Posts: 31
  • Thank you received: 6
  • Karma: 0
Habib

To answer your question, it is archiving which comes after lessons learned that has to be documented. So after documenting, you archive.
Moderators: Yolanda Mabutas, Ahmed Amin, Scott Gillard, Michael DeCicco, Rahul Kakkar, Fernando Jr Sinlao Lim, Mary Kathrine Padua, Chris Preziotti, Lazard Toe, ITBMC, MPM, CIPM, PMP, ITIL, Christian Winter, Kevin Nason, Michael Sumaquial, PMP, Mark Wuenscher, PMP

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®