fbpx
Do you need customer support or technical assistance? Click here to submit a support ticket...

TOPIC: EMV question

EMV question 8 years 7 months ago #6191

  • Ganesh Muniyandy
  • Ganesh Muniyandy's Avatar Topic Author
  • Visitor
  • Visitor
Need answer for the below question which I saw in one of the mobile apps.

You are managing a software engineering project,when two team members come to you with a conflict. The lead developer has identified an important project risk: you have a subcontractor that may not deliver on time. The team estimates that there is a 40% chance that the subcontractor will fail to deliver, if that happens, it will cost an additional $15,250 to pay your work engineers to rewrite the work and the delay will cost the company $20,000 in lost business. Another team member points out an opportunity to save money an another area to offset the risk:if an existing component can be adapted,it will save the project $ 4500 in engineering costs. There is a 65% probability that that team can take advantage of that opportunity. What is the EMV of these two things?

A.-$14,100

B.$6100

C.-$11,175

D.$39,750.

Could you please let me know the answer with an explanation?

Thanks!
Ganesh

EMV question 8 years 7 months ago #6192

  • Rahul Kakkar
  • Rahul Kakkar's Avatar
  • Offline
  • Gold Boarder
  • Gold Boarder
  • Posts: 161
  • Karma: 9
  • Thank you received: 56
Can you quote the name of the mobile app where you got this question?

Answer: C

To calculate the expected monetary value (EMV) of a set of risks and opportunities, multiply each probability by its total cost and add them together. In this question, the cost of the risk is –$15,250 + –$20,000 = –$35,250, so its EMV is 40% x –$35,250 = -$14,100. The value of the opportunity is $4,500 and its probability is 65%, so its EMV is 65% x $4,500 = $2,925. So the total EMV for the two is –$14,100 + $2,925 = –$11,175.
Rahul Kakkar, PMP, MBA
Community Moderator


How are we doing? Your opinion matters. To help us improve, please check out our survey at www.surveymonkey.com/s/pmpexamforum

EMV question 8 years 7 months ago #6193

  • Ganesh Muniyandy
  • Ganesh Muniyandy's Avatar
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 1
  • Thank you received: 0
Thank you Rahul for your answer and explanation.

Name of the mobile app: PMP TEST PREP.
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaDaniel SoerensenAlexander AnikinElena ZelenevskaiaChristian ElmerChristine Whitney, PMP

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login