fbpx
Do you need customer support or technical assistance? Click here to submit a support ticket...

TOPIC: Change Requests - Direct and Manage Project Work

Change Requests - Direct and Manage Project Work 9 years 4 weeks ago #6100

  • Ronald Brierley
  • Ronald Brierley's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 2
  • Thank you received: 0
All-

I wanted to get everyone's thoughts on this one.........I am taking the prepcast course as a refresher for my upcoming PMP exam in two weeks and came across this question in the Scope Management section...........

Question 8: If changes to the project scope are requested by the customer
during the project execution, the changes and their impact must be
analyzed during which process?
A.) Define Scope
B.) Integrated Change Control
C.) Validate Scope
D.) Control Scope

I immediately chose answer B.............but the answer key says answer D.............

I assumed this was a change request and gets submitted right away................

Thanks in advance,

Ron

Change Requests - Direct and Manage Project Work 9 years 3 weeks ago #6101

  • Puneet Singh
  • Puneet Singh's Avatar
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 13
  • Thank you received: 0
Good to know, my exam is also scheduled in couple of weeks...

Question is asking about process where you will analyze impact of scope change.
Control Scope is the process of monitoring the status of the project and product scope and managing changes to the scope baseline. Analysis part is not done by ICCB.

Just to add: This is not yet a change request. Change request should be always documented in detail.

As per my understanding, here is how change request should be submitted:
Document the change request as per project scope management plan -- Analyze the impact on the other factors of triple constraints namely cost and schedule -- Analyze the impact of the change on project quality objectives and quality planning -- Identify Options--Issue change request and send to ICCB -- Document details of change request decision in change logs -- Communicate same to Stakeholders( Manage Stakeholders Engagement).

Thanks,
Puneet

Change Requests - Direct and Manage Project Work 9 years 3 weeks ago #6104

  • Jonathan Emmons
  • Jonathan Emmons's Avatar
  • Offline
  • Senior Boarder
  • Senior Boarder
  • Posts: 41
  • Karma: 1
  • Thank you received: 12
Hi Ron -

Admittedly, on first read I was agreeing with you, but I think this is one of those cases where, as Puneet pointed out, you have to be careful of exactly where you are in the process with regards to how the question is worded.

Here's the explanation for that question from the self-assessment you referenced:

Explanation: The answer should be a monitoring and controlling process. If a change request regarding changes in project scope is requested after the approval of the Scope Baseline, the change request must be analyzed during the Control Scope process before forwarding it to the Integrated Change Control process for approval.
Reference: PMBOK Guide 5th Edition, page 136


In this case, the stakeholder is asking for a change, but this isn't a change request in the formal sense. This would be more like you're having a conversation with the stakeholder, and s/he says "you know what would be great is if we could add a dashboard to that interface ... can we get that added in?"

Now take a look at the first sentence on page 137 of the PMBOK guide: "Controlling the project scope ensures all requested changes and recommended corrective or preventative actions are processed through the Perform Integrated Change Control process." In other words, Controlling Scope is presented as the process in which we catch these conversations before any action is taken, package up the formal change request (including expected impacts), and kick it over to the Perform Integrated Change Control process.

So while it looks like the question is asking "where do we analyze change requests" (in which case the answer would have been B, as you selected), the question is really asking "where do we listen to requests for scope change and package them up as formal change requests" (thus, the correct answer is D). And this makes sense if you think about it in a real-world context - while we say that the CCB is "analyzing" a change request to make a decision, the expectation in the real world is that the PM is already going to have answers to basic questions like "how much will this cost" and "what will this do to our schedule" ready for the CCB to consider.

While I'd love to be able to tell you that the wording on the actual exam will be less nuanced, this isn't always the case - I ran into a few questions like this with regards to the Initiation process group, where it wasn't quite clear which phase we were in and I had to go with my best guess. The good news is that there weren't that many of them, so if you get a few of these wrong in your practice exams, just take note of any gotchas noted in the explanations so you know what to watch for next time, then shake it off and move on.
Jonathan Emmons, PMP
Community Moderator
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaDaniel SoerensenAlexander AnikinElena ZelenevskaiaBrent Lee

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login