2 years 1 month ago #29028

THAMIZHANBAN NATARAJN

THAMIZHANBAN NATARAJN's Avatar

78
2 years 3 months ago #28827

Kanchan Vasnani

's Avatar

the statement says "He has identified 10 stakeholders with whom he needs to communicate"...he cannot communicate with himself, so it makes sense to add him too rather than he including himself identified 10 stakeholders.
3 years 6 months ago #23264

Rajesh

's Avatar

I would consider the key word stakeholders it includes all members in the project including PM. So i would calculate 10+3-1=12 members and apply the formula n(n+1)/2 = 12(12-1)/2= 66
4 years 5 months ago #18733

Anonymous

's Avatar

C
5 years 7 months ago #14892

Anonymous

's Avatar

10 stakeholders identified + 3 = 13 + 1 PM = 14
So 14*13 /2 =91
6 years 2 months ago #12848

IRSHAD

's Avatar

I AGREED.

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login