Hello Mohd,

I have provided a reply to this question in the "free float" discussion thread where you asked it earlier:

www.project-management-prepcast.com/inde...3920-free-float#5117


Regards,
Steve
9 years 2 months ago #5120

Mohd Salik

's Avatar

dear cornellius,
Plz help me solve this question.
In a project, a cost incentive cntract has been awarded to a contractor with the following parameters.

Target Cost : 1,000,000
Target Contractor fees : 100,000

Cost benefit sharing ratio : 80% to 20 %
Price ceiling 1,200,000

What is the PTA of the project.