TOPIC: Question on Contract

Question on Contract 2 years 2 months ago #5120

  • Mohd Salik
  • Mohd Salik's Avatar Topic Author
  • Visitor
  • Visitor
dear cornellius,
Plz help me solve this question.
In a project, a cost incentive cntract has been awarded to a contractor with the following parameters.

Target Cost : 1,000,000
Target Contractor fees : 100,000

Cost benefit sharing ratio : 80% to 20 %
Price ceiling 1,200,000

What is the PTA of the project.

Question on Contract 2 years 2 months ago #5125

  • Steve Sandoval
  • Steve Sandoval's Avatar
  • Offline
  • Senior Boarder
  • Senior Boarder
  • Posts: 49
  • Thank you received: 8
Hello Mohd,

I have provided a reply to this question in the "free float" discussion thread where you asked it earlier:

www.project-management-prepcast.com/inde...3920-free-float#5117


Regards,
Steve
Steve Sandoval, PMP
Community Moderator
  • Page:
  • 1
Moderators: Yolanda MabutasAhmed AminScott GillardMichael DeCiccoRahul KakkarFernando Jr Sinlao LimMary Kathrine PaduaChris PreziottiLazard Toe, ITBMC, MPM, CIPM, PMP, ITILChristian WinterGail FreedmanKevin NasonMichael Sumaquial, PMPSteven Mudrinich, PMPMark Wuenscher, PMP

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®