In a project, a cost incentive cntract has been awarded to a contractor with the following parameters.

Target Cost : 1,000,000
Target Contractor fees : 100,000

Cost benefit sharing ratio : 80% to 20 %
Price ceiling 1,200,000

What is the PTA of the project.

Question on Contract 1 year 8 months ago #5125

  • Steve Sandoval
  • Steve Sandoval's Avatar
  • Offline
  • Senior Boarder
  • Posts: 49
  • Thank you received: 8
  • Karma: 0
Hello Mohd,

I have provided a reply to this question in the "free float" discussion thread where you asked it earlier: