Welcome, Guest
Do you need customer support or technical assistance? Click here to submit a support ticket...

TOPIC: EARNED VALUE CALCULATIONS

EARNED VALUE CALCULATIONS 2 years 1 month ago #4753

  • Ade
  • Ade's Avatar
Good morning all, please is it possible to calculate earned values for all project types. Thank you

EARNED VALUE CALCULATIONS 2 years 1 month ago #4756

  • Michael DeCicco
  • Michael DeCicco's Avatar
  • Offline
  • Moderator
  • Posts: 114
  • Thank you received: 28
  • Karma: 1
Yes. Use the formulas provided through the PMBOK.
here's a quick synopis
Schedule variance: SV = EV - PV (EV is Earned Value, PV is Planned Value)
(Note that SV is always 0 at the end of the project (if the project is completed))
Cost variance: CV = EV - AC (AC is Actual Cost)
(CV at the end of the project is AC - BAC) (BAC is Budget At Completion)
(Both SV and CV should be positive. Negative schedule and cost variance means project is behind schedule and over budget respectively)
Schedule Performance Index: SPI = EV/PV

Cost Performance Index: CPI= EV/AC

If for whatever reason you run a project that doesn't cost "money", you still have some sort of schedule to follow. Use the schedule variance to determine your EV.
Yours Respectfully
Michael DeCicco, PMP
Community Moderator
Moderators: Yolanda Mabutas, Ahmed Amin, Scott Gillard, Michael DeCicco, Rahul Kakkar, Fernando Jr Sinlao Lim, Mary Kathrine Padua, Chris Preziotti, Lazard Toe, ITBMC, MPM, CIPM, PMP, ITIL, Christian Winter, Kevin Nason, Michael Sumaquial, PMP, Mark Wuenscher, PMP

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®