fbpx
Do you need customer support or technical assistance? Click here to submit a support ticket...

TOPIC: EARNED VALUE CALCULATIONS

EARNED VALUE CALCULATIONS 9 years 5 months ago #4753

  • Ade
  • Ade's Avatar Topic Author
  • Visitor
  • Visitor
Good morning all, please is it possible to calculate earned values for all project types. Thank you

EARNED VALUE CALCULATIONS 9 years 5 months ago #4756

  • Michael DeCicco
  • Michael DeCicco's Avatar
  • Offline
  • Expert Boarder
  • Expert Boarder
  • Posts: 130
  • Karma: 12
  • Thank you received: 44
Yes. Use the formulas provided through the PMBOK.
here's a quick synopis
Schedule variance: SV = EV - PV (EV is Earned Value, PV is Planned Value)
(Note that SV is always 0 at the end of the project (if the project is completed))
Cost variance: CV = EV - AC (AC is Actual Cost)
(CV at the end of the project is AC - BAC) (BAC is Budget At Completion)
(Both SV and CV should be positive. Negative schedule and cost variance means project is behind schedule and over budget respectively)
Schedule Performance Index: SPI = EV/PV

Cost Performance Index: CPI= EV/AC

If for whatever reason you run a project that doesn't cost "money", you still have some sort of schedule to follow. Use the schedule variance to determine your EV.
Yours Respectfully
Michael DeCicco, PMP
Community Moderator
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaDaniel SoerensenAlexander AnikinElena ZelenevskaiaChristian ElmerChristine Whitney, PMP

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login