Hi Ivan

Yes it is correct that you can ask a colleague from that time to verify and approve your experience. in the contact relationship use the most appropriate one, in case of colleague or subordinate i think "primary stakeholder" would be a valid choice.


From the PMI FAQ, here is the questions that confirms this:

16. A supervising manager is no longer at the company. How can this project be verified?

The supervising manager can still verify although they are not at the company. If this option is not feasible, a colleague from the project can verify, or a current manager or supervisor, who has intimate knowledge of the project, can verify.
9 years 5 months ago #4683

Ivan Shmilyk

Ivan Shmilyk's Avatar

Thanks again Ahmed, very valuable link and comment!

So is it correct to assume that I can ask my colleague/subordinate from that time to be my contact for PMI audit and state him as my contact, not client?

In the application itself "Contact Relationship" field has only Project Sponsor OR Manager/Director OR Client OR Primary Stakeholder options, and I don't know what to choose, could you please advice?
9 years 5 months ago #4682

Dawn Upperman

Dawn Upperman's Avatar

Hi Ivan,

I totally agree with Ahmed. I was audited as well and it did go very smoothly. Best of luck to you!
9 years 5 months ago #4681

Ahmed Amin

Ahmed Amin's Avatar

Hi Ivan.
please don't freak out, I personally got audited and it went very smooth.

I highly recommend that you read the PMI FAQs about the audit it will clear all your confusions and will let you much more relaxed about the process. you can find the FAQs Here

Regarding your concern, you should fill in all forms and send to client for signing. the client will send you the signed forms back which you will send to the PMI.

I just would like to let you know that you can have any colleague from the project do the approval if he is more reachable that the client, there is no obligation that the client must approve.

Good Luck
9 years 5 months ago #4679

Ivan Shmilyk

Ivan Shmilyk's Avatar

Thanks Ahmed!

My another concern is that the client is located far in foreign country. Now how exactly all this paper based audit process should go? Is it me who sends all the documents for filling and signing to customer, and then he sign them and send back to me in closed envelope? Or does he send anything directly to PMI? And what if those docs are lost along the way?

...frankly speaking all that audit process freaks me out a bit...
9 years 5 months ago #4678

Ahmed Amin

Ahmed Amin's Avatar

Hi Ivan,
I would recommend that you share the same information that you will submit in your PMP application with your previous client. you can have a call or something with him clarifying the information and guiding him through the activities you were doing during the project. you should also let him know that his approval on the same information might be required if you are audited.

Good Luck !