Welcome, Guest
Do you need customer support or technical assistance? Click here to submit a support ticket...

TOPIC: Opportunity to deliver enhanced capacity

Opportunity to deliver enhanced capacity 2 years 4 months ago #4416

  • Subhajit Palit
  • Subhajit Palit's Avatar
  • Offline
  • Fresh Boarder
  • Posts: 8
  • Karma: 0
:unsure:

Question :"You are completing the work defined in the project scope statement of a new software development project when a team member points out that you have an opportunity to deliver enhanced capability to the client at no extra cost, time or risk to the project. What should you do NEXT ?

a> Ignore the request of the team member
b> decline to make changes and proceed to deliver exactly what the scope statement sets out
c> go ahead , make changes and surprise client with the extra capability
d> assess the change via the change control process and if approved amend the project scope statement.

I choose option <b>, but the book says option <d>....... any idea why option <d> is best, as I thought GOLD PLATING should not be entertained........????

Opportunity to deliver enhanced capacity 2 years 4 months ago #4417

  • Cornelius Fichtner
  • Cornelius Fichtner's Avatar
  • Offline
  • Administrator
  • PrepCast Instructor
  • Posts: 981
  • Thank you received: 157
  • Karma: 30
Subhajit,

Before anything else: Please tell us where this question comes from. As an aspiring PMP you always want to attribute copyright and ensure that you give credit where credit is due.

Thank you!
Until Next Time,
Cornelius Fichtner, PMP, CSM
President, OSP International LLC
Last Edit: 2 years 4 months ago by Cornelius Fichtner.

Opportunity to deliver enhanced capacity 2 years 4 months ago #4418

  • Subhajit Palit
  • Subhajit Palit's Avatar
  • Offline
  • Fresh Boarder
  • Posts: 8
  • Karma: 0
Hi Cornelius,

This comes from the book "PMP Examination Practice Questions" for the PMBOK Guide, 5th Edition,by "SEAN WHITAKER" ....> question no# 79, page -29.

Opportunity to deliver enhanced capacity 2 years 4 months ago #4419

  • Cornelius Fichtner
  • Cornelius Fichtner's Avatar
  • Offline
  • Administrator
  • PrepCast Instructor
  • Posts: 981
  • Thank you received: 157
  • Karma: 30
The answer "d) assess the change via the change control process and if approved amend the project scope statement." is indeed correct. Here are my thoughts:
a> Ignore the request of the team member
It would be wrong to simply "ignore" your team member. Everyone has a right to be heard.
b> decline to make changes and proceed to deliver exactly what the scope statement sets out
By declining the idea of the team member offhand like this you are making two mistakes. (1) You dismiss the input from the team member and he will very likely not give future input. (2) You ignore the opportunity to deliver the best possible solution to the customer without even consulting with the customer.
c> go ahead , make changes and surprise client with the extra capability
This is gold plating. Just making the changes without following proper process is wrong.
d> assess the change via the change control process and if approved amend the project scope statement.
This is the correct approach because (1) you are acknowledging that the input from your team member is valid, (2) you accept the fact that change requests can come from any and every stakeholder on the project, (3) you are guiding the change request into the appropriate change control process, and (4) as part of this process you only implement the change AFTER it has been approved by the responsible change control body (which likely includes your customer).
Until Next Time,
Cornelius Fichtner, PMP, CSM
President, OSP International LLC
Last Edit: 2 years 4 months ago by Cornelius Fichtner.
Moderators: Yolanda Mabutas, Ahmed Amin, Scott Gillard, Michael DeCicco, Rahul Kakkar, Fernando Jr Sinlao Lim, Mary Kathrine Padua, Chris Preziotti, Lazard Toe, ITBMC, MPM, CIPM, PMP, ITIL, Christian Winter, Kevin Nason, Michael Sumaquial, PMP, Mark Wuenscher, PMP

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®