Hi Ashwin, if you look on pg 87 of the PMBOK 5th Edition you will see a diagram which shows the flow from 8.3 Control Quality into the 4.4 Monitor & Control Project Work process as work performance information (defects). Also refer to pg 90 in PMBOK 4.4.1.5 Work Performance Information as it helps create "sound foundation for project decisions" as part of the Monitor & Control Project Work. I think if you look at these two pages you will understand that the defects are not happening in 4.3 Direct & Manage Project Work (see pg 61).
9 years 10 months ago #4325

Ashwin Kini

Ashwin Kini's Avatar

I am trying to understand the flow of "defects" on various occasions. Specifically on the Direct and Manage Project Work and Monitor and Control Project Work processes.
In the Direct and Manage Project Work, the work is performed and the output (deliverables) may contain defects. This goes to the Monitor and Control process that checks the deliverables as well? Though I understand the deliverables go to Control Quality (where the defect repairs are reviewed). However, how does this play under the Monitor and Control Project Work process?
My major focus is on the role of defects under the Monitor and Control Project Work process specifically.