TOPIC: Free Float vs. Total Float vs. Project Float

Free Float vs. Total Float vs. Project Float 3 years 1 month ago #4018

  • Sonal Nema
  • Sonal Nema's Avatar
  • Offline
  • Fresh Boarder
  • Posts: 1
  • Karma: 0
Hi

I am struggling to understand the concept of 'float'. Need help understanding the difference between FREE FLOAT, TOTAL FLOAT and PROJECT FLOAT and how each of them is calculated.

I possess the very basic notion on float--

1) Float is the amount of time an activity can be delayed without delaying the start of the immediately following activity.

Float= Late Start (LS) - Early Start (ES)

OR

Float= Late Finish (LF) - Early Finish (EF)

2) Critical Path has zero float
Moderators: Yolanda Mabutas, Ahmed Amin, Scott Gillard, Michael DeCicco, Rahul Kakkar, Fernando Jr Sinlao Lim, Mary Kathrine Padua, Chris Preziotti, Lazard Toe, ITBMC, MPM, CIPM, PMP, ITIL, Christian Winter, Kevin Nason, Michael Sumaquial, PMP, Steven Mudrinich, PMP, Mark Wuenscher, PMP

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

×
Join the upcoming PMP Exam Coaching Class with Coach Dan Ryan. There are 15 seats left in the class! Learn More...