Free Float vs. Total Float vs. Project Float 6 years 9 months ago #4018

  • Sonal Nema
  • Sonal Nema's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 1
  • Thank you received: 0
Hi

I am struggling to understand the concept of 'float'. Need help understanding the difference between FREE FLOAT, TOTAL FLOAT and PROJECT FLOAT and how each of them is calculated.

I possess the very basic notion on float--

1) Float is the amount of time an activity can be delayed without delaying the start of the immediately following activity.

Float= Late Start (LS) - Early Start (ES)

OR

Float= Late Finish (LF) - Early Finish (EF)

2) Critical Path has zero float
Moderators: Yolanda MabutasMary Kathrine PaduaCynthia Lim Louis, PMPTracy Shagnea, PMPGabriella Dellino, PMPPatrick Floris PhD PMPJoe PangJohn Paul BugarinAmy MartinezEmily Rivera, PMPLisa Sweeney PMPHarry ElstonMani SelvanDenver MartinEric Wanyutu Kahiga, PMPSarah FucciThiago França, PMP®Felix Kamanga, PMPChan RampersaudElena MekhanoshinaKyle Kilbride, PMP

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login