The PM PrepCast is closing. All product access ends December 4, 2026.
Until October 31, all products are 50% off.
Read the announcement

Do you need customer support or technical assistance? Click here to submit a support ticket...

TOPIC: Discretionary Dependency in Precedence Diagramming

Discretionary Dependency in Precedence Diagramming 12 years 8 months ago #4013

  • Mehmet Tahir Dede
  • Mehmet Tahir Dede's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 8
  • Thank you received: 1
Hello,
There is a question on EXAM Simulator 3 Question 146 as
What is Discreationary Dependency in Precedence Diagramming Method?

Answer is A Dependency that is established based on knowledge of best practices which is right but the same question has an option as a dependency that is in the poject team' s control.

I think both answers are right?

Can you please explain why a dependency that is in the project team' s control is the wrong answer?

Discretionary Dependency in Precedence Diagramming 12 years 8 months ago #4014

  • Sachin Vehale
  • Sachin Vehale's Avatar
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 16
  • Thank you received: 4
Hi - Both answers are right but 'Answer A' is the BEST answer for this question.

Exam might test you to choose the BEST answer , where all answer options might be correct w.r.t. the question asked.
Moderators: Yolanda Mabutas, Markus Kopko, Mary Kathrine Padua, Professor Kevin Reilly, John Paul Bugarin, Anusha Jayaram, Harry Elston, Jean Kwanda, Neil Baghurst PMP, Elena Zelenevskaia, Erik Smith, Joseph Flanders, Pablo Andres Loayza

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login