Do you need customer support or technical assistance? Click here to submit a support ticket...
  • Page:
  • 1

TOPIC: Question Sample question, not sure I understand the answer

Sample question, not sure I understand the answer 4 years 4 months ago #3521

  • No Longer Active
  • No Longer Active's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 4
  • Thank you received: 0
Hi,

In one of the many sample exams I have done so far, the following question was included ( Oliver Lehmann ):

You found the following earned value analysis information for a project that was recently closed-out: SPI = 0.7, CPI = 1.0

a. The project has been cancelled while it was executed. At that time the project was behind schedule and on budget.
b. The project's deliverables have all been finished. The project came in behind schedule but on budget.
c. The project's deliverables have all been finished. The project came in ahead of schedule but on budget.
d. The project's deliverables have all been finished. The project came in on schedule but over budget.

Am I correct in thinking that the reason that answer "a" is the correct answer is that any project where the SPI (or CPI) is significantly (i.e. more than 0.02 difference) below 1.0 would automatically be cancelled?

Thank you!
Last Edit: by No Longer Active.

Sample question, not sure I understand the answer 4 years 4 months ago #3531

  • Mohammed Almohimeed
  • Mohammed Almohimeed's Avatar
  • Offline
  • Senior Boarder
  • Senior Boarder
  • Posts: 43
  • Thank you received: 1
Hi

I think the answer is either (a) or (B) because we eliminate C,D because the schedule is behind (SPI less than 1)

Still we want to know which is the best answer (a) or (b)

Regards

Sample question, not sure I understand the answer 4 years 4 months ago #3532

  • Mohammed Almohimeed
  • Mohammed Almohimeed's Avatar
  • Offline
  • Senior Boarder
  • Senior Boarder
  • Posts: 43
  • Thank you received: 1
hello


I think the answer is either (a) or (B) because we eliminate C,D because the schedule is behind (SPI less than 1)

Still we want to know which is the best answer (a) or (b)

Regards

Sample question, not sure I understand the answer 4 years 4 months ago #3596

  • Erin Cooke
  • Erin Cooke's Avatar
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 1
  • Thank you received: 1
The answer would be A. They are telling you that the project was canceled, not asking you why. SPI is really an indication of project completion. At the completion of the project the SPI will always be 1.0 regardless of how long it takes to get there. Since this project was closed and the SPI was only 0.71 it indicates that not all project deliverables were completed. Therefore the only possible solution would be A.
The following user(s) said Thank You: Mohammed Almohimeed
  • Page:
  • 1
Moderators: Yolanda MabutasAhmed AminScott GillardMary Kathrine PaduaERIC BARTLETTGail FreedmanKevin NasonSteven Mudrinich, PMPMark Wuenscher, PMPJohn WolvertonTracy Shagnea, PMPJada Garrett

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Boost Your PMP Exam Prep in Only Six Hours! Join the Live PMP Coaching Class on Dec 02/03 for just $79. Learn More...
The PMP Exam is Changing in 2018
Simona and Cornelius
Free Interview - Listen Now

This interview with Simona Fallavollita (LinkedIn Profile) was recorded at the magnificient Project Management Institute (PMI)® Global Conference 2017 in Chicago, Illinois. We discuss the how, what, why and when of the changes that are coming to the PMP exam.

Thank you!
Cornelius Fichtner, PMP, CSM