Welcome, Guest
Do you need customer support or technical assistance? Click here to submit a support ticket...

TOPIC: Sample question, not sure I understand the answer

Sample question, not sure I understand the answer 3 years 5 months ago #3521

  • No Longer Active
  • No Longer Active's Avatar
  • Offline
  • Fresh Boarder
  • Posts: 4
  • Karma: 0
Hi,

In one of the many sample exams I have done so far, the following question was included (Oliver Lehmann):

You found the following earned value analysis information for a project that was recently closed-out: SPI = 0.7, CPI = 1.0

a. The project has been cancelled while it was executed. At that time the project was behind schedule and on budget.
b. The project's deliverables have all been finished. The project came in behind schedule but on budget.
c. The project's deliverables have all been finished. The project came in ahead of schedule but on budget.
d. The project's deliverables have all been finished. The project came in on schedule but over budget.

Am I correct in thinking that the reason that answer "a" is the correct answer is that any project where the SPI (or CPI) is significantly (i.e. more than 0.02 difference) below 1.0 would automatically be cancelled?

Thank you!
Last Edit: 3 years 5 months ago by No Longer Active.

Sample question, not sure I understand the answer 3 years 4 months ago #3531

  • Mohammed Almohimeed
  • Mohammed Almohimeed's Avatar
  • Offline
  • Senior Boarder
  • Posts: 43
  • Thank you received: 1
  • Karma: 0
Hi

I think the answer is either (a) or (B) because we eliminate C,D because the schedule is behind (SPI less than 1)

Still we want to know which is the best answer (a) or (b)

Regards

Sample question, not sure I understand the answer 3 years 4 months ago #3532

  • Mohammed Almohimeed
  • Mohammed Almohimeed's Avatar
  • Offline
  • Senior Boarder
  • Posts: 43
  • Thank you received: 1
  • Karma: 0
hello


I think the answer is either (a) or (B) because we eliminate C,D because the schedule is behind (SPI less than 1)

Still we want to know which is the best answer (a) or (b)

Regards

Sample question, not sure I understand the answer 3 years 4 months ago #3596

  • Erin Cooke
  • Erin Cooke's Avatar
  • Offline
  • Fresh Boarder
  • Posts: 1
  • Thank you received: 1
  • Karma: 0
The answer would be A. They are telling you that the project was canceled, not asking you why. SPI is really an indication of project completion. At the completion of the project the SPI will always be 1.0 regardless of how long it takes to get there. Since this project was closed and the SPI was only 0.71 it indicates that not all project deliverables were completed. Therefore the only possible solution would be A.
The following user(s) said Thank You: Mohammed Almohimeed
Moderators: Yolanda Mabutas, Ahmed Amin, Scott Gillard, Michael DeCicco, Rahul Kakkar, Fernando Jr Sinlao Lim, Mary Kathrine Padua, Chris Preziotti, Lazard Toe, ITBMC, MPM, CIPM, PMP, ITIL, Christian Winter, Kevin Nason, Michael Sumaquial, PMP, Mark Wuenscher, PMP

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®