Am not able to understand what behind Configuration management plan? In PmBok stated:
Configuration management plan. The configuration management plan defines those items
that are configurable, those items that require formal change control, and the process for
controlling changes to such items.


CMP 4 years 11 months ago #3219

  • Cornelius Fichtner
  • Cornelius Fichtner's Avatar
  • Away
  • Administrator
  • Administrator
  • PrepCast Instructor
  • Posts: 1164
  • Karma: 38
  • Thank you received: 197

The best place for you to start is to review E04.05 Integrated Change Control from The PM PrepCast. Here we look at various aspects of change control, including CMS. That will make things clearer for you.
Until Next Time,
Cornelius Fichtner, PMP, CSM
President, OSP International LLC
  • Page:
  • 1
Moderators: Yolanda MabutasTimothy EnallsScott GillardMary Kathrine PaduaERIC BARTLETTKevin NasonSteven Mudrinich, PMPMark Wuenscher, PMPJohn WolvertonTracy Shagnea, PMPJada GarrettMark LacattivaPatrick Floris PhD PMPTy Weston, PMPGenevieve Pluviose, PMP

Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®