4 years 5 months ago #19123 | |
---|---|
pmtycoon
|
Edward I agree with your point, A lot of people here are not explaining to the point.
ETC = BAC - EV let me exemplify how it was derived. lets say you have 100 dollars budgeted work which we call it as BAC BAC = $100 Lets say you spent 50 dollars which is the cost incurred, so the actual cost is now $50 Now lets say the earned value you got is only 20 dollars worth. so now if lets say you have to figure out how much do you need to spend to get the rest of the work completed. so lets first see how much money is with us It is $50 dollars cash remaining because we already spent $50 dollars ($100 - $50). but how much worth of work is remaining. it is ($100 - $20). The worth of work remaining to complete is $80 dollars more. so, if you take $100 dollars what is it? BAC so, if you take $20 dollars what is it? EV so, how much work is still remaining ? ($100 - $20 = $80) = BAC - EV = ETC. ETC = BAC - AC is WRONG. it is NOT estimate to complete but it the remaining budget formula... Remaining BAC = BAC - AC The correct formula is ETC = EAC - AC which is derived from EAC = ETC + AC if not clear, send me an email PMTycoon |
6 years 7 months ago #11816 | |
---|---|
Stephen Hardy
|
Not sure of your question - "A typical" or "atypical" have different meanings and do you mean derive the formula or drive. I will assume you mean a typical case and derive. Hopefully this explains. If not please clarify your question.
Without a formula: ETC = what is our estimate to complete the work from here to the end. Let’s say that we have done very bad so far and spent twice as much as we have earned. (so Earned/Actual = CPI = 0.5). We determine after review that the reasons we did so bad will continue for the remainder of the project and so our ETC is based on the value of work to be earned at 50% efficiency. The earned value or progress of the work to date is a calculated value based on installed or completed work. Let’s say we are 40% complete and so 60% remains to complete the work. Budget for the work is $10,000, so we have earned $4,000 (40%) and need to earn $6,000 to finish the work. It has cost us $8,000 to complete the first 40% of the work (at an efficiency of 50% or CPI of 0.5) and so the remaining $6,000 of earned value will cost us $12,000 at that same efficiency. Which is also the ETC or estimate to complete. Putting these into the official formula ETC = (10,000 - 4000)/0.5 = 12,000 we get the same answer. |
6 years 7 months ago #11793 | |
---|---|
Aws Shehab
|
Please can you explain to me how we drive this formula ETC = (BAC - EV) / CPI or just memorize it like that ? i read many explanation but still i am confused on this point.
|
11 years 2 months ago #3129 | |
---|---|
Cornelius Fichtner
|
Edward,
May I suggest our PMP Exam Formula Study Guide at www.pmformulas.com ? I'm not trying "to make a sale" here, but if you are having trouble understanding the EV formulas, then the formula study guide is a great tool where you have all the formulas in one place. 1) Here is what the formula guide says about these formulas ETC = EAC - AC: Inversion of the same formula from the EAC calculations. Note: This ETC formula is listed in only one (the “most famous”) PMP prep workbook. No others list it. We recommend using it, if no keywords are given. ETC = BAC - EV : Assumption: use formula if current variances are thought to be atypical in the future. ETC = (BAC - EV) / CPI :Assumption: use formula if current variances are thought to be typical in the future. 2) Here is a sample question from our formula study guide: Question 10: PV = 100, EV = 105, BAC = 400, AC = 102, CV = 3, ETC = 300, EAC = 407. The ETC is given as 300. However, how much would the Estimate to Complete be if we assume that current variances are thought to be atypical? and the answer is of course BAC-EV |
11 years 2 months ago #3128 | |
---|---|
Edward Wada
|
I guess I am still confused. So I will go back to my original intended questions.
Question: 1) Can you clarify when we use BAC - EV vs EAC - AC? ( Which of the two should you use? That depends on which two inputs are available to you in the scenario., I understand one uses EV vs AC, but why would one be "atypical"?) 2) Can you give an example question that would we would use EAC - AC? Or if possible, make a slight change in the same question, so we would know when we would use BAC - EV? Please give example questions / scenarios to help clarify. Thank you. |
11 years 2 months ago #3111 | |
---|---|
Khurram Hussain
|
Dear Edward:
Please see my comments inline: "I got the formula from the material, I bought from Cornelius' company (OSP). See exact reference to below. Also I believe on a OSP simulated test, ETC = BAC-AC was referenced." Are you sure the formula for ETC mentioned is BAC - AC. It should be EAC - AC not BAC - AC. Can you please confirm? PMP® Formula Pocket Guide Copyright © 2009-2011 by OSP International LLC. All rights reserved. Version 2.2 - Use with PMBOK® Guide 4th Edition Earned Value ETC = EAC - AC This is correct ETC ‘atypical’ = BAC - EV This is correct ETC ‘typical’ = (BAC - EV) / CPI This is correct ETC ‘flawed’ = new estimate This is correct I hope the reference help? Can you help explain when to use EAC-AC vs BAC - EV on the test now? EAC - AC and BAC - EV are both correct formulas for calculating ETC Let's prove these two formulas are correct. ETC = EAC - AC ETC = (AC + BAC - EV) - AC .... using the formula EAC = AC + BAC - EV [PMBOK4 page: 184] ETC = AC + BAC - EV - AC ETC = BAC - EV So both of these formulas are okay if your are calculating the ETC work to be performed at the budgeted rate. Which of the two should you use? That depends on which two inputs are available to you in the scenario. Please let me know if this helps. Warm regards, Khurram |
OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®
Company Info
- Home
- PMP®
- PMI-ACP®
- CAPM®
- CIPP/E®
- PDUs
- AI
- Free
- Free PM PrepCast Training
- Free PM PrepCast Exam Simulator
- Free PMP® Practice Exam
- The Free PM PrepCast
- Free PMP® Exam Guides
- Free PMP® Exam Newsletter
- Free PMP® Webinars
- All Free PMP® Exam Resources...
- The Free Agile PrepCast
- Free PMI-ACP® Exam Newsletter
- All Free PMI-ACP® Exam Resources...
- Free CAPM® Exam Newsletter
- All Free PDU Resources...
- Corporate
- Articles
- PMP® Study Guide
- PMP® Certification Cost
- 35 Hours of Project Management Education
- Knowledge Areas & Process Groups
- How to Fill in the PMP Application
- PMP® Certification Exam
- How to get PMP Certification
- PMP® ITTO
- PMP® Exam Questions
- PMP® Certification Bangalore
- PMP® Formulas
- Failed PMP Exam
- PMI-ACP Certification Study Guide
- CAPM Certification Study Guide
- 12 Project Management Principles Explained by Experts
- Project Management Certifications Career Advancement
- PMP vs Certifications
- Project Management Organization Company Benefits
- Project Management Organizations Importance
- Reviews
- Forum