Need help with the question yo Calculate pert 4 years 3 months ago #2895

  • Mohammed Chowdhury
  • Mohammed Chowdhury's Avatar
  • Offline
  • Fresh Boarder
  • Posts: 4
  • Karma: 0
O = 4
P = 5
M = 2
what is pert

a. 3.
b. 4
c. 5
d. 6

Thanks

Need help with the question yo Calculate pert 4 years 3 months ago #2896

  • Fnu Riyaz
  • Fnu Riyaz's Avatar
  • Offline
  • Fresh Boarder
  • Posts: 2
  • Karma: 0
Formula for the Program Evaluation and Review Technique

PERT= (O+4M+P)/6

From your Example

PERT= (4+4*2+5)/6 = 2.833 = Rounded 3

Answer is 3

Even can the we can take average of Pessimestic, Optimestic and Most likely.

Formula is

PERT = (P+M+O)/3

PERT = 4+5+2/3

Answer is 3

Please correct me If Am wrong.
Moderators: Yolanda Mabutas, Ahmed Amin, Scott Gillard, Michael DeCicco, Rahul Kakkar, Fernando Jr Sinlao Lim, Mary Kathrine Padua, Chris Preziotti, Lazard Toe, ITBMC, MPM, CIPM, PMP, ITIL, Christian Winter, Kevin Nason, Michael Sumaquial, PMP, Mark Wuenscher, PMP

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®