fbpx
Do you need customer support or technical assistance? Click here to submit a support ticket...

TOPIC: Need help with the question yo Calculate pert

Need help with the question yo Calculate pert 11 years 7 months ago #2895

  • Mohammed Chowdhury
  • Mohammed Chowdhury's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 4
  • Thank you received: 0
O = 4
P = 5
M = 2
what is pert

a. 3.
b. 4
c. 5
d. 6

Thanks

Need help with the question yo Calculate pert 11 years 7 months ago #2896

  • Fnu Riyaz
  • Fnu Riyaz's Avatar
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 2
  • Thank you received: 0
Formula for the Program Evaluation and Review Technique

PERT= (O+4M+P)/6

From your Example

PERT= (4+4*2+5)/6 = 2.833 = Rounded 3

Answer is 3

Even can the we can take average of Pessimestic, Optimestic and Most likely.

Formula is

PERT = (P+M+O)/3

PERT = 4+5+2/3

Answer is 3

Please correct me If Am wrong.
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaDaniel SoerensenElena ZelenevskaiaChristian ElmerChristine Whitney, PMP

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login