TOPIC: Need help with the question yo Calculate pert

Need help with the question yo Calculate pert 4 years 7 months ago #2895

  • Mohammed Chowdhury
  • Mohammed Chowdhury's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 4
  • Thank you received: 0
O = 4
P = 5
M = 2
what is pert

a. 3.
b. 4
c. 5
d. 6

Thanks

Need help with the question yo Calculate pert 4 years 7 months ago #2896

  • Fnu Riyaz
  • Fnu Riyaz's Avatar
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 2
  • Thank you received: 0
Formula for the Program Evaluation and Review Technique

PERT= (O+4M+P)/6

From your Example

PERT= (4+4*2+5)/6 = 2.833 = Rounded 3

Answer is 3

Even can the we can take average of Pessimestic, Optimestic and Most likely.

Formula is

PERT = (P+M+O)/3

PERT = 4+5+2/3

Answer is 3

Please correct me If Am wrong.
  • Page:
  • 1
Moderators: Yolanda MabutasAhmed AminScott GillardMichael DeCiccoRahul KakkarFernando Jr Sinlao LimMary Kathrine PaduaChris PreziottiLazard Toe, ITBMC, MPM, CIPM, PMP, ITILChristian WinterGail FreedmanKevin NasonMichael Sumaquial, PMPSteven Mudrinich, PMPMark Wuenscher, PMP

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®