Do you need customer support or technical assistance? Click here to submit a support ticket...
  • Page:
  • 1

TOPIC: Question Need Clarifications on Simulator Qs.

Need Clarifications on Simulator Qs. 5 years 9 months ago #2864

  • Chaps
  • Chaps's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 7
  • Thank you received: 0

In the Exam 5, in my opinion, the following questions need to be corrected for better language or the choices need to be corrected.

Can someone please take some time to look into this and clarify the same?

1.During the course of a multi-phased project, a project manager extensively uses EVM to determine project statistics and predict future estimates. Durign which of the following processes will the total project's earned value be at its maximum?

A. When closing processes are being performed.
B. When planning processes are being performed.
C. When executing processes are being performed.
D. None of the above.

I chose C) but the correct answer seems to be D). Although I read the explanation, I am not convinced that my choice was incorrect - especially given the language of the query and the choices available.

2. Which of the following is a project constraint?
A. Scope of work
B. Project Requirements
C. Teaming Agreement
D. Organizational Process Assets

I chose (A) but the correct answer seems to be C). Furthermore in the clarification given, we are pointed to PMBOK page 319.

There is no clear mention anywhere in the PMBOK that the teaming agreements are project constraints whereas Scope, Requirements are part of the project constraints is hammered very clearly.

Thanks in advance,

Need Clarifications on Simulator Qs. 4 months 2 weeks ago #12309

  • Nasser
  • Nasser's Avatar
  • Visitor
  • Visitor
Agree with you....the explanation support answer C , however the y mentioned D is correct anwer
  • Page:
  • 1
Moderators: Yolanda MabutasTimothy EnallsScott GillardMary Kathrine PaduaERIC BARTLETTKevin NasonSteven Mudrinich, PMPMark Wuenscher, PMPJohn WolvertonTracy Shagnea, PMPJada GarrettMark LacattivaPatrick Floris PhD PMPTy Weston, PMPGenevieve Pluviose, PMP

Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

The PMP Exam is Changing in 2018
Simona and Cornelius
Free Interview - Listen Now

This interview with Simona Fallavollita (LinkedIn Profile) was recorded at the magnificient Project Management Institute (PMI)® Global Conference 2017 in Chicago, Illinois. We discuss the how, what, why and when of the changes that are coming to the PMP exam.

Thank you!
Cornelius Fichtner, PMP, CSM