fbpx
Do you need customer support or technical assistance? Click here to submit a support ticket...

TOPIC: Output for Direct & Manage Project Process

Output for Direct & Manage Project Process 14 years 9 months ago #281

  • Akshay Chawade
  • Akshay Chawade's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 3
  • Thank you received: 0
Hi,

As per PM PrepCast on Direct & Manage Project process, the listed Outputs of this process includes "Work Perf Info" and "Project Doc Updates". Arent "Work Perf Info" part of Project Docs? Why are they mentioned separatly?

Thanks!
Akshay

Re:Output for Direct & Manage Project Process 14 years 9 months ago #282

  • Cornelius Fichtner
  • Cornelius Fichtner's Avatar
  • Offline
  • Administrator
  • Administrator
  • President, OSP International LLC
  • Posts: 1982
  • Karma: 119
  • Thank you received: 606
Akshay,

Take a look at Figure 4-7 on page 84 of your PMBOK Guide. Here you will see that the Project Document updates and the Work Performance Information are used as inputs to different processes. That is why they are called out separately.
Until Next Time,
Cornelius Fichtner, PMP, CSM
President, OSP International LLC

Re:Output for Direct & Manage Project Process 14 years 9 months ago #283

  • Akshay Chawade
  • Akshay Chawade's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 3
  • Thank you received: 0
Thanks Cornelius!

So is there a distinction in PMBOK that processes are divided based on who will be executing them? E.g. for a small project, a PM would combine Direct & Manage process and Monitor & Control process activities. Where as for a large project, a group of PMs would Direct& Manage their parts, and a Senior PM would take Work Perf Info and do Monitor & Control for overall project.

Thanks!
Akshay

Re:Output for Direct & Manage Project Process 14 years 9 months ago #286

  • Cornelius Fichtner
  • Cornelius Fichtner's Avatar
  • Offline
  • Administrator
  • Administrator
  • President, OSP International LLC
  • Posts: 1982
  • Karma: 119
  • Thank you received: 606
Akshay,

You will find the answer to this question in the PMBOK Guide itself - particularly in the introduction to the knowledge areas. For instance, this is from Time:

On some projects, especially those of smaller scope, defining activities, sequencing activities, estimating activity resources, estimating activity durations, and developing the schedule are so tightly linked that they are viewed as a single process that can be performed by a person over a relatively short period of time. These processes are presented here as distinct processes because the tools and techniques for each are different.


So the question isn't WHO does it but WHAT are they doing, HOW are they doing it and WHAT skills, T&T etc. are being used.
Until Next Time,
Cornelius Fichtner, PMP, CSM
President, OSP International LLC
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaDaniel SoerensenElena ZelenevskaiaChristian ElmerChristine Whitney, PMP

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login