TOPIC: Question on Network Diagram

Question on Network Diagram 12 years 6 months ago #2535

  • Mahesh Kumar S
  • Mahesh Kumar S's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 1
  • Thank you received: 0
I have recently purchased the PMP® Exam Formula Study Guide, which is helping me to identify gaps.
My question is on Network Diagram, while many claims the first activity early start can neither be 0 or 1 & the corresponding results will be the same on either methods. Iam following to adapt 0 days for easy calculation.Which is the correct method & easy to understand?
I would like to mention the one of the question & answer provided in your kit.
Question : The activity “Ship Container” in your network diagram has an early
start of day 17, a late start of day 22 and a late finish of day 37. What is the activity duration?
A.) 15 days
B.) 16 days - Correct Answer
C.) 59 days
D.) 14 days

Based on the Formula guide the formula says Activity Duration=EF - ES + 1 or LF - LS + 1..when translated AD= 37-22+1 = 16. Since iam following "0" to be the ES of my activity my answer would be 15.

This may be the most silly question, but kindly clarify.

Re:Question on Network Diagram 12 years 4 months ago #2632

  • Essam Mohammed
  • Essam Mohammed's Avatar
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 1
  • Thank you received: 0
Please can anybody answer the question because I am also confusing.

Rita follows 0 start and you follow 1 start. What is the correct for the exam?

Thank you

Re:Question on Network Diagram 12 years 4 months ago #2634

  • Cornelius Fichtner
  • Cornelius Fichtner's Avatar
  • Offline
  • Administrator
  • Administrator
  • President, OSP International LLC
  • Posts: 1982
  • Karma: 119
  • Thank you received: 606
Please read the explanation about 0 / 1 start date in our knowledge base at the following URL:

www.pmhelpdesk.com/entries/20346821-why-...ting-es-ef-ls-and-lf
Until Next Time,
Cornelius Fichtner, PMP, CSM
President, OSP International LLC

Re:Question on Network Diagram 12 years 4 months ago #2642

  • Sagar Mainkar
  • Sagar Mainkar's Avatar
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 9
  • Thank you received: 0
I have same confusion and infact our confusion are correct as illustrated by your example we get different answers by different methods which means one of the method is incorrect.
-Sagar

Re:Question on Network Diagram 12 years 4 months ago #2649

  • Sunil Kumar
  • Sunil Kumar's Avatar
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 1
  • Thank you received: 0
I would say no formula is needed for that .. say if you start your activity at day 1 and finish on day 1 .. duration will be 1 day not 0 day. So you have to add a day if you use subtraction method.

I would say what PM Prep Case suggested is right.
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaDaniel SoerensenElena ZelenevskaiaChristian ElmerChristine Whitney, PMP

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login