Pert estimation is the technique of estimating task durations. Once you have these estimates you can then draw either Gantt chart or a Network Diagram using the durations.

en.wikipedia.org/wiki/Program_Evaluation_and_Review_Technique is a good overview of the process.
12 years 8 months ago #2274

Anjali Riat

Anjali Riat's Avatar

Hi,

What is the difference between PERT estimation and PERT network diagram?