TOPIC: PERT

PERT 9 years 2 months ago #2274

  • Anjali Riat
  • Anjali Riat's Avatar Topic Author
  • Offline
  • Junior Boarder
  • Junior Boarder
  • Posts: 21
  • Thank you received: 0
Hi,

What is the difference between PERT estimation and PERT network diagram?

Regards,
Anjali

Re:PERT 9 years 2 months ago #2275

  • Cornelius Fichtner
  • Cornelius Fichtner's Avatar
  • Offline
  • Administrator
  • Administrator
  • President, OSP International LLC
  • Posts: 1727
  • Karma: 67
  • Thank you received: 336
Pert estimation is the technique of estimating task durations. Once you have these estimates you can then draw either Gantt chart or a Network Diagram using the durations.

en.wikipedia.org/wiki/Program_Evaluation_and_Review_Technique is a good overview of the process.
Until Next Time,
Cornelius Fichtner, PMP, CSM
President, OSP International LLC
Moderators: Yolanda MabutasMary Kathrine PaduaCynthia Lim Louis, PMPTracy Shagnea, PMPGabriella Dellino, PMPPatrick Floris PhD PMPJoe PangJohn Paul BugarinAmy MartinezEmily Rivera, PMPLisa Sweeney PMPHarry ElstonMani SelvanDenver MartinEric Wanyutu Kahiga, PMPSarah FucciThiago França, PMP®Felix Kamanga, PMPChan RampersaudElena MekhanoshinaKyle Kilbride, PMP

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login