TOPIC: Apportioned Effort

Apportioned Effort 9 years 4 months ago #2254

  • Anjali Riat
  • Anjali Riat's Avatar Topic Author
  • Offline
  • Junior Boarder
  • Junior Boarder
  • Posts: 21
  • Thank you received: 0
Hi,

I came across the term Apportioned Effort in the PMBOK. Any inputs on what it means?

Thanks in advance,
Anjali

Re:Apportioned Effort 9 years 4 months ago #2256

  • Cornelius Fichtner
  • Cornelius Fichtner's Avatar
  • Offline
  • Administrator
  • Administrator
  • President, OSP International LLC
  • Posts: 1755
  • Karma: 74
  • Thank you received: 345
Anjali,

It's an Earned Value concept that is not that easy to explain. It's a way to measure and assign effort of related tasks. For instance: If you have a quality assurance person reviewing 10 deliverables, then the time that he spends can be apportioned to these 10 deliverables (i.e. 10% to each). In this way, the effort (cost) created by QA gets "assigned" to your 10 deliverables. (This is by no means a perfect explanation, but it gets the basic idea across.)

Here is an overview of the basic Earned Value concepts:
certifedpmp.wordpress.com/2008/09/23/bas...ed-value-management/
Until Next Time,
Cornelius Fichtner, PMP, CSM
President, OSP International LLC
Moderators: Yolanda MabutasMary Kathrine PaduaCynthia Lim Louis, PMPTracy Shagnea, PMPGabriella Dellino, PMPPatrick Floris PhD PMPJoe PangJohn Paul BugarinAmy MartinezEmily Rivera, PMPLisa Sweeney PMPHarry ElstonMani SelvanDenver MartinEric Wanyutu Kahiga, PMPSarah FucciThiago França, PMP®Felix Kamanga, PMPChan RampersaudElena MekhanoshinaKyle Kilbride, PMP

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login