fbpx
Do you need customer support or technical assistance? Click here to submit a support ticket...

TOPIC: Earned Value and CCPM.

Earned Value and CCPM. 12 years 9 months ago #2220

  • Tarek Al-Fahham
  • Tarek Al-Fahham's Avatar Topic Author
  • Offline
  • Senior Boarder
  • Senior Boarder
  • Posts: 71
  • Karma: 3
  • Thank you received: 0
As per my understanding, the CCPM is becomming more and more widely used for optomizing project schedule and resources, and it is more effective measuring and tracking tool than EVM.

But, also, in the PMP Exam, if by any chance I have to choose between CCPM and then I have to select EVM over CCPM.

Please correct me if I am wrong.

Tarek.

Re:Earned Value and CCPM. 12 years 9 months ago #2221

  • Adam Leslie
  • Adam Leslie's Avatar
  • Offline
  • Junior Boarder
  • Junior Boarder
  • Posts: 25
  • Thank you received: 3
It is my understanding that you will not be make to choose. PMI teaches a project management framework that is agnostic in regards to the tools you use. You should know what tool can (and cannot) be used along with its pros and cons, but I highly doubt the exam will ask us if a certain tool or technique is better than another.

It might ask which one is more appropriate in a given situation. In that case, EVM is better suited to contracts (value focused) and CCPM better suited to production work (resource focused).
Regards,

Adam

Re:Earned Value and CCPM. 12 years 9 months ago #2222

  • Tarek Al-Fahham
  • Tarek Al-Fahham's Avatar Topic Author
  • Offline
  • Senior Boarder
  • Senior Boarder
  • Posts: 71
  • Karma: 3
  • Thank you received: 0
Thanks a lot. It is very clear now.

Tarek.

Re:Earned Value and CCPM. 12 years 9 months ago #2223

  • Adam Leslie
  • Adam Leslie's Avatar
  • Offline
  • Junior Boarder
  • Junior Boarder
  • Posts: 25
  • Thank you received: 3
Okay, I think I was a bit off. I reviewed this further, and the PMBOK is emphatic in using EV to determine variances in Control Schedule. See the PM Prepcast E06.06.

So while I still believe it to be true that for the most part PMI does not endorse a major tool or methodology be "better" than another ... there are exceptions.
Regards,

Adam
Last edit: by Adam Leslie.
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaDaniel SoerensenElena ZelenevskaiaChristian ElmerChristine Whitney, PMP

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login