TOPIC: Minus /Plus in Duration equation

Minus /Plus in Duration equation 15 years 3 months ago #2153

  • Saad Al Naib
  • Saad Al Naib's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 6
  • Thank you received: 0
Hi ,

I went through webcast and understand that +1 and -1 point of view.

My question let look at this link:

en.wikipedia.org/wiki/Program_Evaluation_and_Review_Technique

Why such equations that is :

EF = ES + Duration +1

LS = LF -Duration -1

LF = LS of successor -1
ES = EF of predessor +1

From precast is clear how come it is not clear when I see different diagram.

My only explaination is starting first day is day 0 not day 1 which makes is so different from prepcast.

Thank you.

saad
Moderators: Yolanda Mabutas, Markus Kopko, Mary Kathrine Padua, Professor Kevin Reilly, John Paul Bugarin, Anusha Jayaram, Harry Elston, Jean Kwanda, Neil Baghurst PMP, Elena Zelenevskaia, Erik Smith, Joseph Flanders, Pablo Andres Loayza

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login