TOPIC: Minus /Plus in Duration equation

Minus /Plus in Duration equation 9 years 2 months ago #2153

  • Saad Al Naib
  • Saad Al Naib's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 6
  • Thank you received: 0
Hi ,

I went through webcast and understand that +1 and -1 point of view.

My question let look at this link:

en.wikipedia.org/wiki/Program_Evaluation_and_Review_Technique

Why such equations that is :

EF = ES + Duration +1

LS = LF -Duration -1

LF = LS of successor -1
ES = EF of predessor +1

From precast is clear how come it is not clear when I see different diagram.

My only explaination is starting first day is day 0 not day 1 which makes is so different from prepcast.

Thank you.

saad
Moderators: Yolanda MabutasMary Kathrine PaduaCynthia Lim Louis, PMPTracy Shagnea, PMPGabriella Dellino, PMPPatrick Floris PhD PMPJoe PangJohn Paul BugarinAmy MartinezEmily Rivera, PMPLisa Sweeney PMPHarry ElstonMani SelvanDenver MartinEric Wanyutu Kahiga, PMPSarah FucciThiago França, PMP®Felix Kamanga, PMPChan RampersaudElena MekhanoshinaKyle Kilbride, PMP

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login