TOPIC: Activity Duration Equation clarification

Activity Duration Equation clarification 9 years 2 months ago #2147

  • Saad Al Naib
  • Saad Al Naib's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 6
  • Thank you received: 0
Hi ,

Equations of Network Diagram in specific:

- Activity Duration = EF-ES+1
- Activity Duration = LF-LS+1
- ES = EF of predecessor +1
- LF = LS of successor -1

Ex. Page 90 of PMP Certification Mathematics by Vidya And Riva

9 2 11 15 1 16
D F
19 10 21 21 6 22

ES Dur. EF
Task name
LS Slack LF

Why other books like Headfirst explains such concept while others above cannot see it applying. Am I missing something am talking about +1, -1 in the equations above just want to understand this but it seems different diagrams some support such other not why ?


Thank You.


saad
Moderators: Yolanda MabutasMary Kathrine PaduaCynthia Lim Louis, PMPTracy Shagnea, PMPGabriella Dellino, PMPPatrick Floris PhD PMPJoe PangJohn Paul BugarinAmy MartinezEmily Rivera, PMPLisa Sweeney PMPHarry ElstonMani SelvanDenver MartinEric Wanyutu Kahiga, PMPSarah FucciThiago França, PMP®Felix Kamanga, PMPChan RampersaudElena MekhanoshinaKyle Kilbride, PMP

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login