Welcome, Guest
Do you need customer support or technical assistance? Click here to submit a support ticket...

TOPIC: Earned Value and Estimate to Complete in Months.

Earned Value and Estimate to Complete in Months. 5 years 5 months ago #2120

  • Tarek Al-Fahham
  • Tarek Al-Fahham's Avatar
  • Offline
  • Senior Boarder
  • Posts: 71
  • Karma: 3
Ref. to this article (which was referenced in one of the emails from PM PrepCast):

www.projectsmart.co.uk/earned-value-management-explained.html

I learned that:

SP = EV - PV

will give the unit result in Months, but I am not convinced. See the Problem and solution mentioned in the article.

Also, I learned that to calculate the Estimate Months to Completes I use this formula:

Estimate Months to Complete = (BAC - EV) / SPI

Or,

Total Months taking the variance into consideration

New Estimate Total in Months = Original Planned Months / SPI

There is no much reference to such formula anywhere in the net nor in the Formula Study Guide.

I hope my understanding is correct.

In case you have any comment, I appreciate you feedback.

Tarek.
Moderators: Yolanda Mabutas, Ahmed Amin, Scott Gillard, Michael DeCicco, Rahul Kakkar, Fernando Jr Sinlao Lim, Mary Kathrine Padua, Chris Preziotti, Lazard Toe, ITBMC, MPM, CIPM, PMP, ITIL, Christian Winter, Kevin Nason, Michael Sumaquial, PMP, Mark Wuenscher, PMP

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®