fbpx
Do you need customer support or technical assistance? Click here to submit a support ticket...

TOPIC: Scheduling questions

Scheduling questions 12 years 10 months ago #2060

  • James Pfaff
  • James Pfaff's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 2
  • Thank you received: 0
Is it appropriate to ask, in reference to taking the PMP:

1. Will the PMP exam always have a start date of "1", or "0" when thinking of Network Diagraming? Or will it be evident and those particulars will be given/ known within the exam?

Cornelius, I asume you will see this post, and you use the +1 or -1 in your "PMP Formula Pocket Prep Guide", depending on the circumstances.

2. When I see, e.g.: +15, or -10 with leads and lags, are those to be assumed "work days" (Mon-Fri), or "calendar days" (Sun-Sat).

Maybe dumb questions, but gotta ask, since I test on 1 July 2011, I need to clear up any and all concerns...

Congrats to all the recent "Passed PMP exam posts"!!!

Thanks in advance!!!

Jim

Re:Scheduling questions 12 years 10 months ago #2061

  • Cornelius Fichtner
  • Cornelius Fichtner's Avatar
  • Offline
  • Administrator
  • Administrator
  • President, OSP International LLC
  • Posts: 1981
  • Karma: 118
  • Thank you received: 605
James,

I can answer both questions with "it depends on the scenario".

Each PMP Exam question has to be viewed separately. One question will be this way and another question will be that way. It depends 100% on how the question was developed and framed.

My recommendation is always the same: Don't worry too much about how a question could be asked or not asked. The PMP exam doesn't try to "trick" you. It tests your understanding of general PM concepts.

That much said: Each question on the exam will have the correct amount of information needed for you to find the correct answer.
Until Next Time,
Cornelius Fichtner, PMP, CSM
President, OSP International LLC
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaDaniel SoerensenElena ZelenevskaiaChristian ElmerChristine Whitney, PMP

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login