NPV IRR and Payback period 5 years 8 months ago #1869

  • Muhammad Zahid
  • Muhammad Zahid's Avatar
  • Offline
  • Fresh Boarder
  • Posts: 19
  • Karma: 0
i read that during project selection v have to consider larger NPV and IRR while small or little Payback period.so what v have to select in following scenarios.
Project A has NPV and Payback period both are larger then Project B.
so ?

Re:NPV IRR and Payback period 5 years 8 months ago #1870

  • Cornelius Fichtner
  • Cornelius Fichtner's Avatar
  • Offline
  • Administrator
  • PrepCast Instructor
  • Posts: 966
  • Thank you received: 152
  • Karma: 29

Larger NPV = Good
Larger IRR = Good
Larger Payback Period = Bad

So in your example, where project A has a larger NPV and also a larger Payback Period it is impossible to really make a selection:

NPV = Project A has a larger NPV and is therefore better
Payback Period = Project B has a smaller Payback Period and is therefore better

It's impossible to make a final decision just based on these numbers.
Until Next Time,
Cornelius Fichtner, PMP, CSM
President, OSP International LLC